Developer Extension Agreement (DEA) Process – Additional Detail Information
Developer Extension Agreement (Dea) • October 18th, 2022

The Initiation Phase starts the formal Developer Extension Agreement (DEA) process between the Developer and District. The Initiation Phase starts with the Application and ends with an approved DEA and provision of Certificates of Water and/or Sewer Availability.

AutoNDA by SimpleDocs
Developer Extension Agreement (DEA) Process – Additional Detail Information
Developer Extension Agreement (Dea) • October 16th, 2024

The Initiation Phase starts the formal Developer Extension Agreement (DEA) process between the Developer and District. The Initiation Phase starts with the Application and ends with an approved DEA and provision of Certificates of Water and/or Sewer Availability.

Developer Extension Agreement (DEA) Process – Additional Detail Information
Developer Extension Agreement (Dea) • February 15th, 2016

The Pre-Construction Phase includes provision of all required permits and easements, and submittal of documents and guarantees required for the project construction. The Pre-Construction Phase ends with the Pre-Construction meetings.

Developer Extension Agreement (DEA) Process – Additional Detail Information
Developer Extension Agreement (Dea) • February 15th, 2016

The Construction Phase covers all construction, inspection and testing of the new water and/or sewer facilities. At the conclusion of the Construction Phase the facilities should be ready for service.

Developer Extension Agreement (DEA) Process – Additional Detail Information
Developer Extension Agreement (Dea) • August 17th, 2021

The Initiation Phase starts the formal Developer Extension Agreement (DEA) process between the Developer and District. The Initiation Phase starts with the Application and ends with an approved DEA and provision of Certificates of Water and/or Sewer Availability.

Developer Extension Agreement (DEA) Process – Additional Detail Information
Developer Extension Agreement (Dea) • February 15th, 2016

The Acceptance Phase covers provision of submittals and documents representing the water and/or sewer facilities, as constructed. During the Acceptance Phase the District will commence provision of water and/or sewer service to the new development. If final paving is being phased, the Acceptance Phase also includes completion of adjustments of the water and/or sewer facilities in the final pavement.