PIPRT INE ADJUSTMENT AGREEMENT
Pipeline Adjustment Agreement • December 29th, 2023

Pipeline Company for the Estimated Cost within thirty (30) days from the Effective Date of this Agreement. If the Estimated Cost is greater than the actual cost and expense of the Work, Dow will reimburse FBC the difference between the Estimated Cost and the actual cost within ninety (90) days of completion of the Pipeline Adjustment and Work contemplated herein. If the actual cost exceeds the Estimated Cost, FBC will pay the additional amount due within ninety (90) days ofFBC's receipt of all cost records related to the Pipeline Adjustment and Work from Dow; provided however, FBC will not be liable for costs that exceed the Estimated Cost by more than 20% without prior written amendment to this Agreement. Dow shall furnish copies of all cost records to FBC upon written request.