3 Tenants-in-Common Reorganization Agreement Dated May 12, 2014Tenants-in-Common Reorganization Agreement • November 29th, 2015 • Texas
Contract Type FiledNovember 29th, 2015 JurisdictionGENERAL CONTRACTOR COSTS General Contractor Mobilization $ 95,000.00Landscape Restoration 10,000.00Temporary Fencing, Barricades, and Ramps 65,000.0019' to 22' x 8" Cut-Off Wall (TDWC) 692,010.00Drainage Pipe for 19' to 22' x 8" Wall 304,765.00Storm Drain System 839,705.00Demo Existing Storm Drain System 82,766.008" Vertical Realignment 12,000.00Asphalt Patch Back 140,510.00Concrete Trench Patch Back/Sidewalk/Curb 443,796.50 TOTAL DIRECT HARD COSTS $ 2,685,552.50 Performance Bond $ 67,138.81 CONTINGENCY @ 10% Of Total Hard Costs 268,555.00 GC FEE @ 15% of Total Hard Costs 402,833.00Pre-construction Meetings 10,000.00 TOTAL GENERAL CONTRACTOR COSTS $ 3,434,079.31