Delay Event Notice definition
Examples of Delay Event Notice in a sentence
Such Delay Event Notice will include (i) a detailed description of the Delay Event, (ii) details of the circumstances from which the Delay Event arises and (iii) an estimate of the duration of the delay in the performance of obligations pursuant to this Agreement attributable to such Delay Event and information in support thereof, if known at that time.
In the event (ii) and (iii) above are not known at the time of the Delay Event Notice, such notice will be resubmitted within 21 Days of the original Delay Event Notice to include such information.
Such CA Delay Event Notice will include, in such form and substance as is required to satisfy Concessionaire’s obligations under the Comprehensive Agreement: (i) a detailed description of the CA Delay Event, (ii) details of the circumstances from which the CA Delay Event arises and (iii) an estimate of the duration of the delay in the performance of obligations pursuant to this Agreement attributable to such CA Delay Event and information in support thereof, if known at that time.
Based on the CA Delay Event Notice provided by Contractor to Concessionaire hereunder, Concessionaire shall assert its rights thereunder to seek the Department’s approval under Section 13.01 of the Comprehensive Agreement with respect to the CA Delay Event claimed by Contractor.
Subject to Sections 12.14 and 12.15, Concessionaire shall submit a “Delay Event Notice” under Section 13.01 of the Comprehensive Agreement based on the CA Delay Event Notice submitted by Contractor hereunder and thereafter assert its rights under the Comprehensive Agreement with respect to the CA Delay Event claimed by Contractor.
If for any reason the Developer fails to deliver a Delay Event Notice within such 21-Day period, the Developer will be deemed to have irrevocably and forever waived and released any Claim or right to time extensions or any other relief with respect to such Delay Event pursuant to this Agreement or any Project Agreement.
If for any reason Contractor fails to deliver a CA Delay Event Notice within such fifteen (15) day period, Contractor will be deemed to have irrevocably and forever waived and released any Claim or right to time extensions or any other relief with respect to such CA Delay Event pursuant to this Agreement.
Such Delay Event Notice will include (i) a detailed description of the Delay Event, (ii) details of the circumstances from which the Delay Event arises and (iii) an estimate of the duration of the delay in the performance of obligations pursuant to this Agreement attributable to such Delay Event and information in support thereof, if known at that time.
If for any reason the Developer fails to deliver a Delay Event Notice within such 30 Day period (unless the City’s rights are not prejudiced by such delinquent notice or the ability to rectify, remedy or materially mitigate such Delay Event was not impaired), the Developer will be deemed to have irrevocably and forever waived and released any claim or right to time extensions or any other relief with respect to such Delay Event pursuant to this Development Agreement or any related agreement.
The Authority shall, after receipt of the Delay Event Notice, be entitled by notice to require the Lessee to provide such further supporting information as the Authority may reasonably consider necessary.