Final Test definition
Examples of Final Test in a sentence
In case Purchaser will not provide MEI with a Notice of Disapproval within the abovementioned term, Purchaser will automatically waive any and all of its right to object and contest the results of such Final Test which shall have to be considered approved by Purchaser.
In such case, Purchaser shall automatically waive any and all of its right to object and contest the results of the Final Test which shall have to be considered approved by Purchaser; or (ii) at the Delivery Date, in case Purchaser, within 5 (five) calendar days after the Final Test date, will not provide MEI with a reasoned and duly supported written notice rejecting the result of such Final Test (hereinafter, “Notice of Disapproval”).
If the Final Test Results reveal that the relevant Block has satisfied the Minimum Capacity Level but not the Guaranteed Capacity (as adjusted for uncertainty in accordance with Exhibit 16A), Contractor may elect to perform additional Work (if it deems necessary) and repeat the Capacity Test.
All Tests shall be conducted in accordance with the Final Test Plan for such Test, provided that such Final Test Plan is consistent with the requirements of Part I.A above.
Contractor shall, as soon as practicable following the completion of a Capacity Test in which the Final Test Results reveal that the Minimum Capacity Level for such Block has been achieved, submit to Owner's Representative a Capacity Test Certificate, signed by Contractor's Representative and attaching the Final Test Results performed pursuant to Exhibit 16A.
The Final Test Plan from the Commercial Operation Test for the Initial Compliance Test shall be used for the Initial Compliance Test, unless the Parties agree otherwise in writing.
If the Final Test Results reveal that the relevant Block fails to meet the Minimum Capacity Level for such Block, Contractor shall repeat the respective Capacity Test as many times as necessary until the Minimum Capacity Level has been met.
The Final Test Plan from the Commercial Operation Test for the Contract Capacity Test shall be used for the Contract Capacity Test, unless the Parties agree otherwise in writing.
The Final Test Plan from the Commercial Operation Test shall be used for the Efficiency Rate Test, unless the Parties agree otherwise in writing.
Within ten (10) Business Days after ▇▇▇▇▇’s receipt of Seller’s Proposed Test Plan, Buyer shall notify Seller that (i) the Seller’s Proposed Test Plan is accepted, and is now considered the Final Test Plan, or (ii) the Seller’s Proposed Test Plan is not accepted.