Contractor shall provide Owner with Notice at least one hundred eighty (180) Days’ prior to the date on which Contractor expects LNG Storage Tank Cooldown to occur and shall specify in such Notice the amount of Feed Gas required for LNG Storage Tank Cooldown.
Not less than ninety (90) Days and not more than one hundred twenty (120) Days after such Notice, Contractor shall give Owner a second Notice specifying the seven (7) Day period during which Contractor expects LNG Storage Tank Cooldown to occur and confirming the amount of Feed Gas required for LNG Storage Tank Cooldown.
Contractor is responsible for the procurement of Equipment, bulk materials and consumable items necessary to construct, pre-commission, commission, start up, and operate Train 4 and LNG Storage Tank up to SC of Train 4, as further defined hereafter.
Such plan shall be in sufficient detail to allow for Owner to schedule for providing the means for the removal of LNG from the LNG Storage Tank, whether by LNG Tankers or otherwise.
At least [***] ([***]) months prior to RLFC, Contractor shall prepare and provide Owner with Contractor’s LNG production plan, prepared by Contractor using GECP, detailing Contractor’s estimated production of LNG prior to Substantial Completion, including the dates and volumes of LNG to be produced and the dates in which it forecasts that such LNG would need to be removed from the LNG Storage Tank to allow for such LNG production.
Contractor shall provide all pre-commissioning, commissioning, testing and start-up spare parts necessary for Train 4 and LNG Storage Tank to achieve SC and shall, prior to and as a condition precedent to achieving RLFC for Train 4, deliver such spare parts for Train 4 to the Site, including all Work related to procuring and storing the commissioning spare parts.
Control scheme validation study Surge analysis of rundown lines (LNG Train to LNG Storage Tank) Process engineering shall include verification of tie-ins between Train 4 and Phase 1 Facilities.
Contractor shall provide Owner with [***] ([***]) Days prior written notice of its intent to perform the LNG Storage Tank Pump-Out Rate Performance Test.
Company intends to develop a greenfield LNG facility, gas conditioning facilities, power generation facilities, LNG truck loading terminal, comprising two (2) liquefaction units with a nominal average design capacity of three (3) million seven (7) hundred thousand gallons per day, six (6) million gallon LNG Storage Tank and associated facilities for the purpose of liquefying natural gas supplied from the ▇▇▇▇▇▇▇▇ pipeline and loading such LNG into trucks.
Contractor shall utilize an LNG Tanker that arrives at the Train 4 Facility after RLFC to perform the LNG Storage Tank Pump-Out Rate Performance Test (as defined in Attachment S) in accordance with the requirements of this Agreement, including Attachment S.