Owner’s Right to Stop Work Sample Clauses

Owner’s Right to Stop Work. The Owner reserves the right, for itself and for any designated Construction Inspector retained by Owner, upon observation of apparent nonconforming Work, to immediately stop the affected Work. If the Work is later determined by the Design Professional to be in fact conforming Work, then Contractor shall be entitled upon timely claim to a Change Order for payment by Owner of any reasonable Actual Costs actually incurred by Contractor in connection with the stop Work order and resumption of the Work, as well as an extension in the time for performance of the Work to the extent Contractor is delayed by Owner's stop Work order. The Design Professional shall determine the time, which shall be binding upon both Owner and Contractor, as set forth in Section 3, Part 3.
AutoNDA by SimpleDocs
Owner’s Right to Stop Work. Owner may, without cause and for its convenience, order Design-Builder in writing to stop and suspend the Work. Such suspension shall not exceed sixty (60) consecutive Days or aggregate more than ninety (90) Days during the duration of the Project. Design-Builder is entitled to seek an adjustment of the Contract Price and/or the Contract Time(s) if its cost or time to perform the Work has been adversely impacted by any suspension or stoppage of work by Owner.
Owner’s Right to Stop Work. If the Design-Builder fails to correct Work which is not in accordance with the requirements of the Design-Build Documents as required by Section 11.2 or persistently fails to carry out Work in accordance with the Design-Build Documents, the Owner may issue a written order to the Design-Builder to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Design-Builder or any other person or entity, except to the extent required by Section 5.13.1.3.
Owner’s Right to Stop Work. If the Contractor fails to correct Work which is not in accordance with requirements of the Contract Documents or persistently fails to carry out Work in accordance with the Contract Documents, the Owner may order the Contractor to stop work or any portion thereof until the cause of such order has been eliminated. Such an order must be in writing.
Owner’s Right to Stop Work. Owner may, without cause and for its convenience, order Vendor in writing to stop and suspend performance of the Scope of Work. Such suspension shall not exceed [*] consecutive Days or aggregate more than [*] Days during the duration of the Project, and Owner shall provide Vendor with fifteen (15) Days notice to resume the performance of the Scope of Work. Vendor shall be entitled to an adjustment of the Contract Price, Work Schedule or other affected terms and conditions in accordance with Article 14 if its cost or time to perform the Work has been adversely impacted by any suspension or stoppage of work by Owner.
Owner’s Right to Stop Work. Owner shall have the right to order Contractor to stop all or any portion of the Work if at any time Owner reasonably determines that Contractor’s performance of the Work is not in compliance with the requirements of the Contract Documents. Such noncompliance shall include Contractor’s failure to provide adequate labor, materials or equipment to satisfactorily maintain the various Project schedules (including the construction schedule). This right to stop the Work shall be exercised, if at all, solely for Owner’s benefit and nothing herein shall be construed as obligating Owner to exercise this right for the benefit of Contractor or any other person.
Owner’s Right to Stop Work. 11.1.1 Owner may, without cause and for its convenience, order Design-Builder in writing to stop and suspend the Work. Such suspension shall not exceed sixty (60) consecutive days or aggregate more than ninety (90) days during the duration of the Project. 11.1.2 Design-Builder is entitled to seek an adjustment of the Contract Price and/or Contract Time(s) if its cost or time to perform the Work has been adversely impacted by any suspension of stoppage of the Work by Owner which is not caused by the acts of the Design Builder or its agents, Consultants or Subcontractors.
AutoNDA by SimpleDocs
Owner’s Right to Stop Work. A. 2.4.1 If the Design-Builder fails to correct Work which is not in accordance with the requirements of the Design-Build Documents or persistently fails to carry out Work in accordance with the Design- Build Documents, the Owner may issue a written order to the Design-Builder to stop the Work, or any portion thereof, until the cause for such order has been eliminated.
Owner’s Right to Stop Work. 11.1.1 Owner may, without cause and for its convenience, order Design-Builder in writing to stop and suspend its Work. 11.1.2 Design-Builder may seek an adjustment of the Guaranteed Maximum Price or Contract Time(s) of performance or both under Article 9 of the General Conditions to the extent that its Work has been adversely impacted by any suspension or stoppage of work by Owner, unless actions or inactions of the Design-Builder are the cause of the Owner stopping the Work.
Owner’s Right to Stop Work. 9.1.1 Owner may, without cause and for its convenience, order Xxxxxx Mechanical in writing to stop and suspend the Work. Such suspension shall not exceed ninety (90) consecutive days or aggregate more than one hundred fifty (150) days during the duration of the Project. 9.1.2 Xxxxxx Mechanical is entitled to seek an adjustment of the Contract Price and/or Contract Time(s) if its cost or time to perform the Work has been adversely impacted by any suspension of stoppage of work by Owner not resulting from the fault of Xxxxxx Mechanical or its. Design Consultants, Subcontractors, or others of those for whom Xxxxxx Mechanical is responsible.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!