252 Physical Change. (a) Forest Ser- vice shall adjust the Specified Road construction cost if, prior to acceptance under B6.36, a physical change, caused by a single event and not due to negligence of Contractor, results in an increase or decrease in work and/or materials furnished by Contractor involving addi- tional estimated cost of: (i) More than $10,000 or (ii) More than 10 percent of total Specified Road construction cost, whichever is less.
Appears in 10 contracts
Samples: Integrated Resource Timber Contract, Integrated Resource Timber Contract, Integrated Resource Timber Contract
252 Physical Change. (a) Forest Ser- vice shall adjust the Specified Road construction cost if, prior to acceptance under B6.36BT6.36, a physical change, caused by a single event and not due to negligence of ContractorCon- tractor, results in an increase or decrease in work and/or materials furnished by Contractor involving addi- tional estimated additional esti- mated cost of:
(i) More than $10,000 or
(ii) More than 10 percent of total Specified Road construction cost, whichever is less.of:
Appears in 6 contracts
Samples: Integrated Resource Contract, Integrated Resource Timber Contract, Integrated Resource Timber Contract