Common use of Accelerations for Owner’s Convenience Clause in Contracts

Accelerations for Owner’s Convenience. 11.9.1 In the event Owner desires to accelerate the Project Schedule for reasons other than delays caused by or attributable to the Contractor, Owner shall so notify Contractor in writing. 11.9.2 Upon receipt of such written instruction, Contractor shall require its personnel and its Subcontractors and Vendors to work such overtime hours and/or to increase their respective work forces as are reasonably necessary to meet Owner’s acceleration goals. 11.9.3 In the event such an acceleration is ordered by Owner, Contractor shall be entitled to an adjustment in the Guaranteed Maximum Price determined in accordance with Article 18 of this Agreement.

Appears in 3 contracts

Samples: Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Design Build Agreement (Wynn Resorts LTD)

AutoNDA by SimpleDocs

Accelerations for Owner’s Convenience. 11.9.1 In the event Owner desires to accelerate the Project Schedule for reasons other than delays caused by or attributable to the Contractor, Owner shall so notify Contractor in writing. 11.9.2 Upon receipt of such written instruction, Contractor shall require its personnel and its Subcontractors and Vendors to work such overtime hours and/or to increase their respective work forces as are reasonably necessary to meet Owner’s acceleration goals. 11.9.3 In the event such an acceleration is ordered by Owner, Contractor shall be entitled to an adjustment in the Original Project Guaranteed Maximum Price or Expansion Project Guaranteed Maximum Price (as applicable) determined in accordance with Article 18 of this Agreement.

Appears in 1 contract

Samples: Design Build Agreement (Wynn Resorts LTD)

AutoNDA by SimpleDocs

Accelerations for Owner’s Convenience. 11.9.1 In the event Owner desires to accelerate the Project Schedule for reasons other than delays caused by or attributable to the Contractor, Owner shall so notify Contractor in writing. 11.9.2 Upon receipt of such written instruction, Contractor shall require its personnel and its Subcontractors and Vendors to work such overtime hours and/or to increase their respective work forces as are reasonably necessary to meet Owner’s 's acceleration goals. 11.9.3 In the event such an acceleration is ordered by Owner, Contractor shall be entitled to an adjustment in the Guaranteed Maximum Price determined in accordance with Article 18 of this Agreement.

Appears in 1 contract

Samples: Guaranteed Maximum Price Construction Services Agreement (Wynn Resorts LTD)