Acceptance of Final Payment. 78.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officials, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 and Article 77. 78.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this Article, or those for amounts deducted by the Commissioner from the final requisition or from the final payment as approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding. 78.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon. 78.4. The Contractor, however, shall not be barred by this Article from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 and Article 77 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 8 contracts
Samples: Supply and Service Agreement, Furnish and Install Agreement, Furnish and Install Agreement
Acceptance of Final Payment. 78.165.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officialsofficial, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 and Article 7764.
78.265.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this Article, or those for amounts deducted by the Commissioner from the final requisition or by the Comptroller from the final payment as approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding.
78.365.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.465.4. The Contractor, however, shall not be barred by this Article from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s substantial and 's final requisitions pursuant to Article 76 and Article 77 64 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 6 contracts
Samples: Supply and Service Agreement, Management and Operation Agreement, Supply and Service Agreement
Acceptance of Final Payment. 78.179.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officials, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 77 and Article 7778.
78.279.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this ArticleArticle 79, or those for amounts deducted by the Commissioner from the final requisition or from the final payment as certified by the Engineer or Project Manager and approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding.
78.379.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.479.4. The Contractor, however, shall not be barred by this Article 79 from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 77 and Article 77 78 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 3 contracts
Samples: Furnish and Install Agreement, Furnish and Install Agreement, Furnish and Install Agreement
Acceptance of Final Payment. 78.1. 46.1 The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officials, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 Articles 44 and Article 7745.
78.2. 46.2 The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this ArticleArticle 46, or those for amounts deducted by the Commissioner from the final requisition or from the final payment as certified by the Engineer and approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding.
78.3. 46.3 Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.4. 46.4 The Contractor, however, shall not be barred by this Article 46 from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s 's substantial and final requisitions pursuant to Article 76 Articles 44 and Article 77 45 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT the contracting Agency and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 3 contracts
Samples: Proposal for Bids, Standard Construction Contract, Construction Contract
Acceptance of Final Payment. 78.146.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officials, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 Articles 44 and Article 7745.
78.246.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this ArticleArticle 46, or those for amounts deducted by the Commissioner from the final requisition or from the final payment as certified by the Engineer and approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding.
78.346.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.446.4. The Contractor, however, shall not be barred by this Article 46 from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s 's substantial and final requisitions pursuant to Article 76 Articles 44 and Article 77 45 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT the contracting Agency and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Acceptance of Final Payment. 78.177.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any courtCourt, or otherwise, shall constitute and operate as a release of to the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officialsofficers, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 75 and Article 7776.
78.277.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this Article, or those for amounts deducted by the Commissioner from the final requisition or by the Comptroller from the final payment as approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any officialofficer, agent or employee of the City to the contrary notwithstanding.
78.377.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.477.4. The Contractor, however, shall not be barred by this Article from commencing an action for breach of Contract under this provision to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 and Article 77 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 2 contracts
Samples: Furnish and Install Agreement, Furnish and Install Agreement
Acceptance of Final Payment. 78.165.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officials, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions requisition pursuant to Article 76 and Article 7764.
78.265.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this ArticleArticle 65, or those for amounts deducted by the Commissioner from the final requisition or from the final payment as certified by the Engineer or Project Manager and approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding.
78.365.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.465.4. The Contractor, however, shall not be barred by this Article 65 from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s substantial and final requisitions requisition pursuant to Article 76 and Article 77 64 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 1 contract
Samples: Supply and Service Agreement
Acceptance of Final Payment. 78.165.1. The acceptance by the Contractor, or by anyone claiming by or through it, of the final payment, whether such payment be made pursuant to any judgment of any court, or otherwise, shall constitute and operate as a release of the City from any and all claims of and liability to the Contractor for anything heretofore done or furnished for the Contractor relating to or arising out of this Contract and the Work done hereunder, and for any prior act, neglect or default on the part of the City or any of its officialsofficial, agents or employees, excepting only a claim against the City for the amounts deducted or retained in accordance with the terms and provisions of this Contract or by Law, and excepting any claims, not otherwise waived, or any pending dispute resolution procedures which are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 and Article 7764.
78.265.2. The Contractor is warned that the execution by it of a release, in connection with the acceptance of the final payment, containing language purporting to reserve claims other than those herein specifically excepted from the operation of this Article, or those for amounts deducted by the Commissioner from the final requisition or by the Comptroller from the final payment as approved by the Commissioner, shall not be effective to reserve such claims, anything stated to the Contractor orally or in writing by any official, agent or employee of the City to the contrary notwithstanding.
78.365.3. Should the Contractor refuse to accept the final payment as tendered by the Comptroller, it shall constitute a waiver of any right to interest thereon.
78.465.4. The Contractor, however, shall not be barred by this Article from commencing an action for breach of Contract to the extent permitted by Law and by the terms of the Contract for any claims that are contained in the verified statement filed with the Contractor’s substantial and final requisitions pursuant to Article 76 and Article 77 64 or that arose after submission of the final payment requisition, provided that a detailed and verified statement of claim is served upon NYCDOT BUILDINGS and Comptroller not later than forty (40) Days after the making of such final payment by electronic funds transfer (EFT) or the mailing of such final payment. The statement shall specify the items upon which the claim will be based and any such claim shall be limited to such items.
Appears in 1 contract