Common use of Access to Right of Way Clause in Contracts

Access to Right of Way. DB Contractor shall be entitled to a Change Order for delays to a Critical Path due to failure of TxDOT to make available a portion of the Schematic ROW, or any Additional Properties that must be acquired due to a TxDOT- Directed Change, Force Majeure Event, or a Necessary Basic Configuration Change, only to the extent provided in Sections 4.4.5.3 and 4.6.9.5 of the General Conditions (as amended by this Design-Build Agreement) and subject to the requirements of Section 4.6 of the General Conditions. 6.5.1 Section 4.6.9.5 of the General Conditions is amended as follows: (i) underlined text is hereby added to Section 4.6.9.5 of the General Conditions and (ii) stricken text is hereby deleted from Section 4.6.9.5 of the General Conditions:

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

AutoNDA by SimpleDocs

Access to Right of Way. DB Contractor shall be entitled to a Change Order for delays to a Critical Path due to failure of TxDOT to make available a portion of the Schematic ROW, or any Additional Properties that must be acquired due to a TxDOT- TxDOT-Directed Change, Force Majeure Event, or a Necessary Basic Configuration Change, only to the extent as provided in Sections 4.4.5.3 and Section 4.6.9.5 of the General Conditions (as amended by this Design-Build Agreement) and subject to the requirements of Section 4.6 of the General Conditions, unless otherwise specified in this Section 6.5. 6.5.1 Section 4.6.9.5 of the General Conditions is amended as follows: (i) underlined text is hereby added to Section 4.6.9.5 of the General Conditions and (ii) stricken text is hereby deleted from Section 4.6.9.5 of the General Conditions:

Appears in 1 contract

Samples: Design Build Agreement

AutoNDA by SimpleDocs

Access to Right of Way. β€Œ DB Contractor shall be entitled to a Change Order for delays to a Critical Path due to failure of TxDOT to make available a portion of the Schematic ROW, or any Additional Properties that must be acquired due to a TxDOT- Directed Change, Force Majeure Event, or a Necessary Basic Configuration Change, only to the extent as provided in Sections 4.4.5.3 and Section 4.6.9.5 of the General Conditions (as amended by this Design-Build Agreement) and subject to the requirements of Section 4.6 of the General Conditions, unless otherwise specified in this Section 6.5. 6.5.1 Section 4.6.9.5 of the General Conditions is amended as follows: (i) underlined text is hereby added to Section 4.6.9.5 of the General Conditions and (ii) stricken text is hereby deleted from Section 4.6.9.5 of the General Conditions:

Appears in 1 contract

Samples: Design Build Agreement