Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event: (a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and (b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a).
Appears in 3 contracts
Samples: Study Agreement, Study Agreement, Study Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a14.2(a).
Appears in 3 contracts
Samples: Framework Agreement, Framework Agreement, Framework Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a11.2(a).
Appears in 2 contracts
Samples: Operation Plan Agreement, Study Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a)12.1.
Appears in 2 contracts
Samples: Organisation Services Agreement, Organisation Services Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance perfor- xxxxx of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations obli- gations under Clause 12.2(a)14.2(a) of this Agreement.
Appears in 1 contract
Samples: Archeological Services Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours reasonaeblendeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(aClause12.2(a).
Appears in 1 contract
Samples: Study Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a)15.2(a) of this Agreement.
Appears in 1 contract
Samples: Geodetic Reference Network Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations ob- ligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a).
Appears in 1 contract
Samples: Study Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon assoon as practicable and use reasonable endeavours reasonableendeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(aClause14.2(a).
Appears in 1 contract
Samples: Framework Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure ForceMajeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a)Clause12.2(a) of this Agreement.
Appears in 1 contract
Samples: Consultancy Service Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and preventand mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good witGh ood Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with complywith its obligations under Clause 12.2(aClause12.2(a).
Appears in 1 contract
Samples: Study Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a16.2(a).
Appears in 1 contract
Samples: Framework Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a11.2a( ).
Appears in 1 contract
Samples: Study Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) : take reasonable steps to prevent and mitigate the consequences of such an event upon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to perform; and
(b) and not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a16.2(a).
Appears in 1 contract
Samples: Framework Agreement
Action on Becoming Aware of Force Majeure. Each Party shall at all times, following the occurrence of a Force Majeure Event:
(a) take reasonable steps to prevent and mitigate the consequences of such an event upon evenut pon the performance of its obligations under this Agreement, resume performance of its obligations affected by the Force Majeure Event as soon as practicable and use reasonable endeavours in accordance with Good Industry Practice to remedy its failure to performtoperform; and
(b) not be relieved from liability under this Agreement to the extent that it is not able to perform, or has not in fact performed, its obligations under this Agreement due to any failure to comply with its obligations under Clause 12.2(a)Clause12.2(a) of this Agreement.
Appears in 1 contract
Samples: Rams Consultancy Services Agreement