Amending and Supplementing the Contract. A. The Contract may be amended or supplemented by a Change Order, a Work Change Directive, a Field Order, or a written amendment signed by Owner and Contractor, including but not limited to the GMP Amendment and any Early Work Package Amendments.
B. If a supplement to the Contract includes a change in the GMP or Contract Times, and is not a part of the GMP Amendment or an Early Work Package Amendment, such supplement must be set forth in a Change Order.
C. All changes to the Contract must be approved by the Owner.
Amending and Supplementing the Contract.
A. The Contract may be amended or supplemented by a Change Order, a Work Change Directive, or a Field Order.
B. If an amendment or supplement to the Contract includes a change in the Contract Price or the Contract Times, such amendment or supplement must be set forth in a Change Order.
C. All changes to the Contract that involve (1) the performance or acceptability of the Work,