Application for Extension of Time. 13.8.1 Before the Contractor's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: (a) The Contractor; the registration number; and Project description; 13.8.1 (b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1 (c) Original total bid price; (d) The original Contract start date and completion date; (e) Any previous time extensions granted (number and duration); and 13.8.1(f) The extension of time requested. 13.8.2 In addition, the application for extension of time shall set forth in detail: 13.8.2 (a) The nature of each alleged cause of delay in completing the Work; (b) The date upon which each such cause of delay began and ended and the number of Days attributable to each such cause; (c) A statement that the Contractor waives all claims except for those delineated in the application, and the particulars of any claims which the Contractor does not agree to waive. For time extensions for Substantial Completion and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and (d) A statement indicating the Contractor's understanding that the time extension is granted only for purposes of permitting continuation of Contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Appears in 8 contracts
Samples: Proposal for Bids, Proposal for Bids, Construction Contract
Application for Extension of Time. 13.8.1 13.8.1. Before the Contractor's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
(a) The Contractor; the registration number; and Project description; 13.8.1
(b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1
(c) Original total bid price;
(d) The original Contract start date and completion date;
(e) Any previous time extensions granted (number and duration); and 13.8.1(f) The extension of time requested.
13.8.2 13.8.2. In addition, the application for extension of time shall set forth in detail: 13.8.2
(a) The nature of each alleged cause of delay in completing the Work;
(b) The date upon which each such cause of delay began and ended and the number of Days attributable to each such cause;
(c) A statement that the Contractor waives all claims except for those delineated in the application, and the particulars of any claims which the Contractor does not agree to waive. For time extensions for Substantial Completion and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and
(d) A statement indicating the Contractor's understanding that the time extension is granted only for purposes of permitting continuation of Contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Appears in 3 contracts
Samples: Construction Contract, Supply and Service Agreement, Contract
Application for Extension of Time. 13.8.1 Before the Contractor's ’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
(a) The Contractor; the registration number; and Project description; 13.8.1
(b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1
(c) Original total bid price;
(d) The original Contract start date and completion date;
(e) Any previous time extensions granted (number and duration); and 13.8.1(f) The extension of time requested.
13.8.2 In addition, the application for extension of time shall set forth in detail: 13.8.2
(a) The nature of each alleged cause of delay in completing the Work;
(b) The date upon which each such cause of delay began and ended and the number of Days attributable to each such cause;
(c) A statement that the Contractor waives all claims except for those delineated in the application, and the particulars of any claims which the Contractor does not agree to waive. For time extensions for Substantial Completion and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and
(d) A statement indicating the Contractor's ’s understanding that the time extension is granted only for purposes of permitting continuation of Contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Appears in 1 contract
Samples: Proposal for Bids
Application for Extension of Time. 13.8.1 Before the Contractor's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
(a) The Contractor; the registration number; and Project description; 13.8.1
(b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1
(c) Original total bid price;
(d) The original Contract start date and completion date;
(e) Any previous time extensions granted (number and duration); and 13.8.1(f) The extension of time requested.
13.8.2 In addition, the application for extension of time shall set forth in detail: 13.8.2:
(a) The nature of each alleged cause of delay in completing the Work;
(b) The date upon which each such cause of delay began and ended and the number of Days attributable to each such cause;
(c) A statement that the Contractor waives all claims except for those delineated in the application, and the particulars of any claims which the Contractor does not agree to waive. For time extensions for Substantial Completion and final completion payments, the application shall include a detailed statement of the dollar amounts of each element of claim item reserved; and
(d) A statement indicating the Contractor's understanding that the time extension is granted only for purposes of permitting continuation of Contract performance and payment for Work performed and that the City retains its right to conduct an investigation and assess liquidated damages as appropriate in the future.
Appears in 1 contract
Samples: Standard Construction Contract