Extension of time for completion. (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely:
(a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv);
(b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13);
(c) occurrence of a Force Majeure Event;
(d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and
(e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement.
(ii) The Contractor shall, no later than 15 (fifteen) business days from the occurrence of an event or circumstance specified in Clause 10.5 (i), inform the Authority’s Engineer by notice in writing, with a copy to the Authority, stating in reasonable detail with supporting particulars, the event or circumstances giving rise to the claim for Time Extension in accordance with the provisions of this Agreement. Provided that the period of 15 (fifteen) business days shall be calculated from the date on which the Contractor became aware, or should have become aware, of the occurrence of such an event or circumstance. Provided further that notwithstanding anything to the contrary contained in this Agreement, Time Extension shall be due and applicable only for the Works which are affected by the aforesaid events or circumstances and shall not in any manner affect the Project Completion Schedule for and in respect of the Works which are not affected hereunder.
(iii) On the failure of the Contractor to issue to the Authority’s Engineer a notice in accordance with the provisions of Clause 10.5 (ii) within the time specified therein, the Contractor shall not be entitled to any Time Extension and shall forfeit its right for any such claims in future. For the avoidance of doubt, in the event of failure of the Contractor to issue notice as specified in this clause 10.5 (iii), the Authority shall be discharged from all liability in connection with the claim.
(iv) The Authority’s Engineer shall, on receipt of the claim in accordance with the provisions of Clause 10....
Extension of time for completion. Add at the end of Sub-Clause 44.1 the following: “Neither rains falling within the rainy seasons as occurs in Kenya nor floods caused by such rains shall be deemed exceptional weather conditions such as may fairly entitle the Contractor to an extension of time for the completion of the work.”
Extension of time for completion. (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv); (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13); (c) occurrence of a Force Majeure Event; (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site; and (e) any other cause or delay which entitles the Contractor to Time Extension in accordance with the provisions of this Agreement.
Extension of time for completion. The Contractor shall be entitled subject to this sub-clause 8.4 [Extension of Time for Completion] to an extension of the Time for Completion if and to the extent that completion for the purposes of sub-clause 10.1 [Taking Over of the Works and Sections] is delayed by any of the following causes (and would not otherwise have been delayed):
(a) a Variation (unless an adjustment to the Time for Completion has been agreed under sub-clause 13.3 [Variation Procedure]);
(b) a cause of delay giving an entitlement to extension of time under a sub-clause of these Conditions; or
(c) any delay, impediment or prevention caused by or attributable to the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site. and the Contractor's entitlement shall be adjusted accordingly to the extent that it has failed to meet these requirements. For the avoidance of doubt, the Contractor shall not be entitled to claim any Costs or extension of time or other relief or compensation for using Prudent Practices, and any grant of an extension of time does not confer or imply the existence of any right of the Contractor to receive compensation from the Employer. The Contractor shall not be entitled to an extension of time in the circumstances of (a) to
Extension of time for completion. If the scope or duration of the Services is increased:
(a) The Consultants shall inform the Client of the circumstances and probable effects in writing.
(b) The increase shall be regarded as Additional Services; and
(c) The Client shall extend the time for Completion of the Services accordingly.
Extension of time for completion. If, subject to the provisions of the Contract, the Engineer orders alterations or additions in the Works in accordance with Clause 48 hereof, or if circumstances constituting force majeure as defined in the Contract have occurred, the Contractor shall be entitled to apply for an extension of the time for completion of the Works specified in the Contract. The Employer shall, upon such application, determine the period of any such extension of time; provided that in the case of alterations or additions in the Works, the application for such an extension must be made before the alterations or additions in the Works are undertaken by the Contractor.
Extension of time for completion. In the event the Contractor is entitled to any extension of time (the “EOT”) for Completion if and to the extent that completion for the purposes of - Clause 2.5.4, SECTION II is or will be delayed by any of the following causes:
Extension of time for completion. In the event of:
(a) the amount or nature of extra or additional work,
(b) any cause of delay referred to in these Conditions,
(c) exceptionally adverse climatic conditions,
(d) any delay, impediment or prevention by the Employer, or
(e) other special circumstances which may occur, other than through a default of or breach of contract by the Contractor or for which he is responsible, being such as fairly to entitle the Contractor to an extension of the Time for Completion of the Works, or any Section or part thereof, the Engineer shall, after due consultation with the Employer and the Contractor, determine the amount of such extension and shall notify the Contractor accordingly, with a copy to the Employer.
Extension of time for completion. The Contractor shall be entitled subject to this sub-clause 8.4 [Extension of Time for Completion] to an extension of the Time for Completion if and to the extent that completion for the purposes of sub-clause 10.1 [Taking Over of the Works and Sections] is delayed by any of the following causes (and would not otherwise have been delayed):
(a) a Variation (unless an adjustment to the Time for Completion has been agreed under sub-clause 13.3 [Variation Procedure]);
(b) a cause of delay giving an entitlement to extension of time under a sub-clause of these Conditions; or
(c) any delay, impediment or prevention caused by or attributable to the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site. The Contractor shall not be entitled to an extension of time in the circumstances of (a) to
Extension of time for completion. Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely: