Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying: 46.8.1.1. The Contractor; the registration number; and Project description; 46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;
Appears in 5 contracts
Samples: Furnish and Install Agreement, Furnish and Install Agreement, Furnish and Install Agreement
Application for Extension of Time. 46.8.1. 13.8.1 Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
46.8.1.1. (a) The Contractor; the registration number; and Project description;
46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;
Appears in 3 contracts
Samples: On Call Cable Infrastructure Installation Services Agreement, Autoclave Sterilizer Maintenance and Repair Agreement, Agreement for Boilers, Heaters, Repairs and Maintenance Services
Application for Extension of Time. 46.8.113.8.1. Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
46.8.1.1. (a) The Contractor; the registration number; and Project description;
46.8.1.2. ; 13.8.1(b) Liquidated damage assessment rate, as specified in the Contract; 13.8.1(c) Original total bid price;
13.8.1 (d) The original Contract start date and completion date;
Appears in 2 contracts
Samples: Standard Construction Contract, Supply and Service Agreement
Application for Extension of Time. 46.8.1. 13.8.1 Before the Contractor’s 's time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
46.8.1.1. The Contractor; the registration number; and Project description;
46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;
Appears in 1 contract
Samples: Construction Contract
Application for Extension of Time. 46.8.1. Before the Contractor’s time extension request will be considered, the Contractor shall notify the ACCO of the condition which allegedly has caused or is causing the delay, and shall submit a written application to the ACCO identifying:
46.8.1.1. The Contractor; the registration number; and Project description;
46.8.1.2. Liquidated damage assessment rate, as specified in the Contract;
Appears in 1 contract
Samples: Furnish and Install Agreement