Application Review Phase. 1. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Project Developers for completeness and then establishes the validity of such submitted Applications, beginning with a deficiency review, as follows: a. Transmission Provider will exercise Reasonable Efforts to inform Applicant of Application deficiencies within 15 Business Days after the Application Deadline. b. Applicant then has 10 Business Days to respond to Transmission Provider’s deficiency determination. c. Transmission Provider then will exercise Reasonable Efforts to review Applicant’s response within 15 Business Days, and then will either validate or reject the Application. 2. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Eligible Customers for completeness and then establishes the validity of such submitted Applications. 3. Transmission Provider will only review an Application during the Application Review Phase following the Application Deadline for which the Application was submitted and deemed complete, which will extend for 90 days or the amount of time it takes to complete all Application review activities for the relevant Cycle, whichever is greater. 4. During the Application Review Phase, and at least 30 days prior to initiating Phase I of the Cycle, Transmission Provider will post the Phase I Base Case data for review, subject to CEII protocols. 5. In the case of an Application for a Generating Facility, the Application Review Phase will include a Site Control review for the Generating Facility. Specifically, Applicant shall provide Site Control evidence, as set forth in Tariff, Part VII, Subpart A, section 302, for at least a one-year term beginning from the Application Deadline, for 100 percent of the Generating Facility site including the location of the high-voltage side of the Generating Facility’s main power transformer(s). In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings. The Site Control requirement in the Application includes an acreage requirement for the Generating Facility, as set forth in the PJM Manuals. 6. In the case of an Application for Merchant Transmission, the Application Review Phase will include a Site Control review for the site of the HVDC converter station(s), phase angle regulator (PAR), and/or variable frequency transformer, as applicable. Specifically, Applicant shall provide Site Control evidence, as set forth in Tariff, Part VII, Subpart A, section 302, for at least a one-year term beginning from the Application Deadline, for 100 percent of the site. In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings.
Appears in 3 contracts
Samples: Generation Interconnection Procedures, Generation Interconnection Procedures, Generation Interconnection Procedures
Application Review Phase. 1. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Project Developers for completeness and then establishes the validity of such submitted Applications, beginning with a deficiency review, as follows:
a. Transmission Provider will exercise Reasonable Efforts to inform Applicant of Application deficiencies within 15 Business Days after the Application Deadline.
b. Applicant then has 10 Business Days to respond to Transmission Provider’s deficiency determination.
c. Transmission Provider then will exercise Reasonable Efforts to review Applicant’s response within 15 Business Days, and then will either validate or reject the Application.
2. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Eligible Customers for completeness and then establishes the validity of such submitted Applications.
3. Transmission Provider will only review an Application during the Application Review Phase following the Application Deadline for which the Application was submitted and deemed complete, which will extend for 90 days or the amount of time it takes to complete all Application review activities for the relevant Cycle, whichever is greater.
4. During the Application Review Phase, and at least 30 days prior to initiating Phase I of the Cycle, Transmission Provider will post the Phase I Base Case data for review, subject to CEII protocols.
5. In the case of an Application for a Generating Facility, the Application Review Phase will include a Site Control site control review for the Generating Facility. Specifically, Applicant shall provide Site Control site control evidence, as set forth in Tariff, Part VIIVIII, Subpart A, section 302C, for at least a one-year term beginning from the Application Deadline, for 100 percent 100% of the Generating Facility site including the location of the high-voltage side of the Generating Facility’s main power transformer(s). In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control site control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings. The Site Control site control requirement in the Application includes an acreage requirement for the Generating Facility, as set forth in the PJM Manuals.
6. In the case of an Application for Merchant Transmission, the Application Review Phase will include a Site Control site control review for the site of the HVDC converter station(s), phase angle regulator (PAR), and/or variable frequency transformer, as applicable. Specifically, Applicant shall provide Site Control evidence, as set forth in Tariff, Part VII, Subpart A, section 302, for at least a one-year term beginning from the Application Deadline, for 100 percent of the site. In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings.as
Appears in 1 contract
Samples: Generation Interconnection Procedure
Application Review Phase. 1. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Project Developers for completeness and then establishes the validity of such submitted Applications, beginning with a deficiency review, as follows:
a. Transmission Provider will exercise Reasonable Efforts to inform Applicant of Application deficiencies within 15 Business Days after the Application Deadline.
b. Applicant then has 10 Business Days to respond to Transmission Provider’s deficiency determination.
c. Transmission Provider then will exercise Reasonable Efforts to review Applicant’s response within 15 Business Days, and then will either validate or reject the Application.
2. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Eligible Customers for completeness and then establishes the validity of such submitted Applications.
3. Transmission Provider will only review an Application during the Application Review Phase following the Application Deadline for which the Application was submitted and deemed complete, which will extend for 90 days or the amount of time it takes to complete all Application review activities for the relevant Cycle, whichever is greater.
4. During the Application Review Phase, and at least 30 days prior to initiating Phase I of the Cycle, Transmission Provider will post the Phase I Base Case data for review, subject to CEII protocols.
5. In the case of an Application for a Generating Facility, the Application Review Phase will include a Site Control site control review for the Generating Facility. Specifically, Applicant shall provide Site Control site control evidence, as set forth in Tariff, Part VII, Subpart A, section 302C, for at least a one-year term beginning from the Application Deadline, for 100 percent 100% of the Generating Facility site including the location of the high-voltage side of the Generating Facility’s main power transformer(s). In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control site control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings. The Site Control site control requirement in the Application includes an acreage requirement for the Generating Facility, as set forth in the PJM Manuals.
6. In the case of an Application for Merchant Transmission, the Application Review Phase will include a Site Control site control review for the site of the HVDC converter station(s), phase angle regulator (PAR), and/or variable frequency transformer, as applicable. Specifically, Applicant shall provide Site Control evidence, as set forth in Tariff, Part VII, Subpart A, section 302, for at least a one-year term beginning from the Application Deadline, for 100 percent of the site. In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings.as
Appears in 1 contract
Samples: Generation Interconnection Procedure
Application Review Phase. 1. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Project Developers for completeness and then establishes the validity of such submitted Applications, beginning with a deficiency review, as follows:
a. Transmission Provider will exercise Reasonable Efforts to inform Applicant of Application deficiencies within 15 Business Days after the Application Deadline.
b. Applicant then has 10 Business Days to respond to Transmission Provider’s deficiency determination.
c. Transmission Provider then will exercise Reasonable Efforts to review Applicant’s response within 15 Business Days, and then will either validate or reject the Application.
2. After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Eligible Customers for completeness and then establishes the validity of such submitted Applications.
3. Transmission Provider will only review an Application during the Application Review Phase following the Application Deadline for which the Application was submitted and deemed complete, which will extend for 90 days or the amount of time it takes to complete all Application review activities for the relevant Cycle, whichever is greater.
4. During the Application Review Phase, and at least 30 days prior to initiating Phase I of the Cycle, Transmission Provider will post the Phase I Base Case data for review, subject to CEII protocols.
5. In the case of an Application for a Generating Facility, the Application Review Phase will include a Site Control site control review for the Generating Facility. Specifically, Applicant shall provide Site Control site control evidence, as set forth in Tariff, Part VII, Subpart A, section 302C, for at least a one-year term beginning from the Application Deadline, for 100 percent 100% of the Generating Facility site including the location of the high-voltage side of the Generating Facility’s main power transformer(s). In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control site control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings. The Site Control site control requirement in the Application includes an acreage requirement for the Generating Facility, as set forth in the PJM Manuals.
6. In the case of an Application for Merchant Transmission, the Application Review Phase will include a Site Control site control review for the site of the HVDC converter station(s), phase angle regulator (PAR), and/or variable frequency transformer, as applicable. Specifically, Applicant shall provide Site Control site control evidence, as set forth in Tariff, Part VII, Subpart A, section 302C, for at least a one-year term beginning from the Application Deadline, for 100 percent 100% of the site. In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control site control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings.
Appears in 1 contract
Samples: Generation Interconnection Procedure
Application Review Phase. (1. .) After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Project Developers for completeness and then establishes the validity of such submitted Applications, beginning with a deficiency review, as follows:
a. a.) Transmission Provider will exercise Reasonable Efforts to inform Applicant of Application deficiencies within 15 Business Days after the Application Deadline.
b. b.) Applicant then has 10 Business Days to respond to Transmission Provider’s deficiency determination.
c. c.) Transmission Provider then will exercise Reasonable Efforts to review Applicant’s response within 15 Business Days, and then will either validate or reject the Application.
(2. .) After the close of the Application Deadline, Transmission Provider will begin the Application Review Phase, wherein Transmission Provider reviews Applications received from Eligible Customers for completeness and then establishes the validity of such submitted Applications.
(3. .) Transmission Provider will only review an Application during the Application Review Phase following the Application Deadline for which the Application was submitted and deemed complete, which will extend for 90 days or the amount of time it takes to complete all Application review activities for the relevant Cycle, whichever is greater.
(4. .) During the Application Review Phase, and at least 30 days prior to initiating Phase I of the Cycle, Transmission Provider will post the Phase I Base Case data for review, subject to CEII protocols.
(5. .) In the case of an Application for a Generating Facility, the Application Review Phase will include a Site Control site control review for the Generating Facility. Specifically, Applicant shall provide Site Control site control evidence, as set forth in Tariff, Part VII, Subpart A, section 302C, for at least a one-year term beginning from the Application Deadline, for 100 percent 100% of the Generating Facility site including the location of the high-voltage side of the Generating Facility’s main power transformer(s). In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control site control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings. The Site Control site control requirement in the Application includes an acreage requirement for the Generating Facility, as set forth in the PJM Manuals.
(6. .) In the case of an Application for Merchant Transmission, the Application Review Phase will include a Site Control site control review for the site of the HVDC converter station(s), phase angle regulator (PAR), and/or variable frequency transformer, as applicable. Specifically, Applicant shall provide Site Control site control evidence, as set forth in Tariff, Part VII, Subpart A, section 302C, for at least a one-year term beginning from the Application Deadline, for 100 percent 100% of the site. In addition, Applicant shall provide a certification, executed by an officer or authorized representative of Applicant, verifying that the Site Control site control requirement is met. Further, at Transmission Provider’s request, Applicant shall provide copies of landowner attestations or county recordings.
Appears in 1 contract
Samples: Generation Interconnection Procedure