Applications by the Company for Consents Sample Clauses

Applications by the Company for Consents. (a) After the Project Effective Date the Company shall make or cause to be made, in a timely fashion, all applications (whether initial or renewal applications) for the Consents specified in Schedule 1 in the Prescribed Form and with the Prescribed Fee to the appropriate Relevant Authorities and shall diligently pursue all such applications. The Company shall use all reasonable efforts to obtain at the earliest possible date. The information supplied in the applications shall be complete and accurate and all such information and all designs, structures, undertakings, activities, construction and other matters proposed, described or identified therein shall satisfy the substantive and procedural requirements of the applicable Laws of Bangladesh applied in a “non-discriminatory” manner.
AutoNDA by SimpleDocs
Applications by the Company for Consents. The Company shall make or cause to be made, in a timely fashion, all applications (whether initial or renewal applications) for the Consents set forth in Schedule 1 (together with any other Consent (if any) identified by the Company which the Company reasonably believes it is required to obtain in connection with the Project) in the prescribed form and with the prescribed fee to the appropriate Public Sector Entities and shall diligently pursue all such applications. The information supplied in the applications shall be complete and accurate and shall satisfy the substantive and procedural requirements of the applicable Laws of Liberia as applied to the Company in a non- discriminatory manner.
Applications by the Company for Consents. The Company shall make or cause to be made, in a timely fashion, all applications (whether initial or renewal applications) for the Company Consents in the Prescribed Form and with the Prescribed Fee to the appropriate Relevant Authority and shall diligently pursue all such applications. The information supplied in the applications shall be complete and accurate and shall satisfy the substantive and procedural requirements of the applicable Laws of Pakistan applied in a “non-discriminatory” manner.

Related to Applications by the Company for Consents

  • TERMINATION BY THE CONTRACTOR If the Work is stopped for a period of thirty days under an order of any court or other public authority having jurisdiction, or as a result of an act of government, such as a declaration of a national emergency making materials unavailable, through no act or fault of the Contractor or a Subcontractor or their agents or employees or any other persons performing any of the Work under a contract with the Contractor, or if the Work should be stopped for a period of thirty days by the Contractor because the Architect has not issued a Certificate for Payment as provided in Paragraph 9.7 of these General Conditions or because the State has not made payment thereon as provided in Paragraph 9.7, then the Contractor may, upon seven additional days written notice to the State and the Architect, terminate the Contract and recover from the State payment for all Work executed and for any proven loss sustained upon any materials, equipment, tools, construction equipment and machinery, including reasonable profit and damages.

Time is Money Join Law Insider Premium to draft better contracts faster.