Common use of Applications for Utility Permits Clause in Contracts

Applications for Utility Permits. 5.5.8.1 It is anticipated that during the design and construction phases of the Work, from time to time Utility Owners may apply to IFA for utility permits to install new Utilities that would cross or longitudinally occupy the Project Right of Way, or to modify, upgrade, relocate or expand existing Utilities within the Project Right of Way for reasons other than accommodation of the Project. The provisions of Sections 5.5.8.2 through 5.5.8.4 shall apply to all such permit applications, except as otherwise provided in Section 5.5.8.5. Except as otherwise provided in Section 5.5.8.4(b) or in Article 15 with respect to a Relief Event under clause (h) of the definition of Relief Event (development or operation of a Business Opportunity), no accommodation of new Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation, time extension or other Claim hereunder. 5.5.8.2 For all such utility permit applications pending as of or submitted after the Effective Date, Developer shall furnish the most recent Project design information and/or as-built plans, as applicable, to the applicants, and shall assist each applicant with information regarding the location of other proposed and existing Utilities. Developer shall keep records of its costs related to new Utilities separate from other costs. 5.5.8.3 Developer, at its cost, shall assist IFA in deciding whether to approve a permit described in Section 5.5.8.

Appears in 5 contracts

Samples: Public Private Agreement, Public Private Agreement, Public Private Agreement

AutoNDA by SimpleDocs

Applications for Utility Permits. β€Œ 5.5.8.1 It is anticipated that during the design and construction phases of the Work, from time to time Utility Owners may apply to IFA for utility permits to install new Utilities that would cross or longitudinally occupy the Project Right of Way, or to modify, upgrade, relocate or expand existing Utilities within the Project Right of Way for reasons other than accommodation of the Project. The provisions of Sections 5.5.8.2 through 5.5.8.4 shall apply to all such permit applications, except as otherwise provided in Section 5.5.8.5. Except as otherwise provided in Section 5.5.8.4(b) or in Article 15 with respect to a Relief Event under clause (h) of the definition of Relief Event (development or operation of a Business Opportunity), no accommodation of new Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation, time extension or other Claim hereunder. 5.5.8.2 For all such utility permit applications pending as of or submitted after the Effective Date, Developer shall furnish the most recent Project design information and/or as-built plans, as applicable, to the applicants, and shall assist each applicant with information regarding the location of other proposed and existing Utilities. Developer shall keep records of its costs related to new Utilities separate from other costs. 5.5.8.3 Developer, at its cost, shall assist IFA in deciding whether to approve a permit described in Section 5.5.8.

Appears in 2 contracts

Samples: Public Private Agreement, Public Private Agreement

Applications for Utility Permits. 5.5.8.1 It is anticipated that during the design and construction phases of the Work, from time to time Utility Owners may apply to IFA for utility permits to install new Utilities that would cross or longitudinally occupy the Project Right of Way, or to modify, upgrade, relocate or expand existing Utilities within the Project Right of Way for reasons other than accommodation of the ProjectEast End Crossing. The provisions of Sections 5.5.8.2 through 5.5.8.4 shall apply to all such permit applications, except as otherwise provided in Section 5.5.8.5. Except as otherwise provided in Section 5.5.8.4(b) or in Article 15 with respect to a Relief Event under clause (h) of the definition of Relief Event (development or operation of a Business Opportunity), no accommodation of new Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation, time extension or other Claim hereunder. 5.5.8.2 For all such utility permit applications pending as of or submitted after the Effective Date, Developer shall furnish the most recent Project East End Crossing design information and/or as-built plans, as applicable, to the applicants, and shall assist each applicant with information regarding the location of other proposed and existing Utilities. Developer shall keep records of its costs related to new Utilities separate from other costs. 5.5.8.3 Developer, at its cost, shall assist IFA in deciding whether to approve a permit described in Section 5.5.8.

Appears in 2 contracts

Samples: Public Private Agreement, Public Private Agreement

AutoNDA by SimpleDocs

Applications for Utility Permits. 5.5.8.1 It is anticipated that during the design and construction phases of the Work, from time to time Utility Owners may apply to IFA for utility permits to install new Utilities that would cross or longitudinally occupy the Project Right of Way, or to modify, upgrade, relocate or expand existing Utilities within the Project Right of Way for reasons other than accommodation of the ProjectEast End Crossing. The provisions of Sections 5.5.8.2 through 5.5.8.4 shall apply to all such permit applications, except as otherwise provided in Section 5.5.8.5. Except as otherwise provided in Section 5.5.8.4(b) or in Article 15 with respect to a Relief Event under clause (h) of the definition of Relief Event (development or operation of a Business Opportunity), no accommodation of new Utilities or of modifications, upgrades, relocations or expansions of existing Utilities pursuant hereto shall entitle Developer to additional compensation, time extension or other Claim hereunder. 5.5.8.2 For all such utility permit applications pending as of or submitted after the Effective Date, Developer shall furnish the most recent Project East End Crossing design information and/or as-built plans, as applicable, to the applicants, and shall assist each applicant with information regarding the location of other proposed and existing Utilities. Developer shall keep records of its costs related to new Utilities separate from other costs. 5.5.8.3 Developer, at its cost, shall assist IFA in deciding whether to approve a permit described in Section 5.5.8.to

Appears in 1 contract

Samples: Public Private Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!