Both. The Contractor shall bear all cost for such insurance as provided in Section 1-07.10. No Claim shall be allowed because of any ambiguity in the Contract if: 1. The Bidder discovers an ambiguity but fails to notify the Contracting Agency; or 2. The Bidder failed to discover a patent ambiguity that would be discovered by a reasonably prudent contractor in preparing its Bid. Any prospective Bidder desiring an explanation or interpretation of the Bid Documents, must request the explanation or interpretation in writing soon enough to allow a written reply to reach all prospective Bidders before the submission of their Bids. Oral explanations, interpretations, or instructions given by anyone before the Award of a Contract will not be binding on the Contracting Agency. Any information given a prospective Bidder concerning any of the Bid Documents will be furnished to all prospective Bidders as an Addendum if that information is deemed by the Contracting Agency to be necessary in submitting Bids or if the Contracting Agency concludes that the lack of the information would be prejudicial to other prospective Bidders.
Appears in 3 contracts
Samples: Standard Specifications for Road, Bridge, and Municipal Construction, Standard Specifications for Road, Bridge, and Municipal Construction, Standard Specifications for Road, Bridge, and Municipal Construction
Both. The Contractor shall bear all cost for such insurance as provided in Section 1-07.10. No Claim shall be allowed because of any ambiguity in the Contract contract if:
1. The Bidder bidder discovers an ambiguity but fails to notify the Contracting Agency; or
2. The Bidder bidder failed to discover a patent ambiguity that would be discovered by a reasonably prudent contractor in preparing its Bidbid. Any prospective Bidder bidder desiring an explanation or interpretation of the Bid Documentsbid documents, must request the explanation or interpretation in writing soon enough to allow a written reply to reach all prospective Bidders bidders before the submission of their Bidsbids. Oral explanations, interpretations, or instructions given by anyone before the Award award of a Contract contract will not be binding on the Contracting Agency. Any information given a prospective Bidder bidder concerning any of the Bid Documents bid documents will be furnished to all prospective Bidders bidders as an Addendum addendum if that information is deemed by the Contracting Agency to be necessary in submitting Bids bids or if the Contracting Agency concludes that the lack of the information would be prejudicial to other prospective Biddersbidders.
Appears in 1 contract
Samples: Standard Specifications for Road, Bridge, and Municipal Construction