Calculating Time. Except as otherwise expressly stated, all “days” referred to in this Contract shall be calendar days. If the last day of any period falls on a weekend day, federal holiday or other day that the Company is closed, the period shall expire the next working day after such day. To determine Company work schedules, consult the xxx.xxxxxx.xxx website under shipping information.
Calculating Time. If anything is permitted or required to be done:
(a) a number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date; Example: if the Settlement Date falls on a Friday, 2 days before the Settlement Date is Wednesday.
(b) at least" a number of days or Business Days before a specified date or a clear number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date and excluding the day on which the thing may or must be done; Example: if the Settlement Date falls on a Friday, at least 2 days before the Settlement Date or 2 clear days before the Settlement Date is Tuesday.
(c) a number of days or Business Days after a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date. Example: if the Contract Date falls on a Monday, 2 days after the Contract Date is Wednesday.
Calculating Time. If anything is permitted or required to be done:
Calculating Time. If anything is permitted or required to be done:
(a) a number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date; Example: if the Settlement Date falls on a Friday, 2 days before the Settlement Date is Wednesday.
(b) at least" a number of days or Business Days before a specified date or a clear number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date and excluding the day on which the thing may or must be done; Example: if the Settlement Date falls on a Friday, at least 2 days before the Settlement Date or 2 clear days before the Settlement Date Day”) will be treated as given or delivered at 9am on the second Business Day.
Calculating Time. If anything is permitted or required to be done:
(a) a number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date; Example: if the Settlement Date falls on a Friday, 2 days before the Settlement Date is Wednesday.
(b) for amounts to be paid to destination accounts other than the Buyer's Solicitor's trust account, the Seller must give the Buyer a copy of the current account for the Outgoing to enable the Buyer to verify the destination account details in the Financial Settlement Schedule.
Calculating Time. If the time for performance of any obligation hereunder expires on typical Business Day, the time for performance shall be extended to the next Business Day. For purposes of this Agreement, a “Business Day” shall be defined as any time from 8:00
a. m. through 4:30 p.m. on a Monday, Tuesday, Wednesday, Thursday, or Friday, excluding Federally recognized holidays or days closed due to events or effects that can neither be anticipated nor controlled such as floods, earthquakes, riots, strikes, or other acts of force majeure. Any reference to “day” or “Days” in this Agreement shall be construed as Business Days.
Calculating Time. If anything is permitted or required to be done:
(a) a number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date; Example: if the Settlement Date falls on a Friday, 2 days before the Settlement Date is Wednesday. Workspace or otherwise to enable settlement to occur on the Settlement Date.
Calculating Time. Except as otherwise expressly stated, all “days” referred to in this Contract shall be calendar days. If the last day of any period falls on a weekend day, federal holiday or other day that Aerojet Rocketdyne, Inc. is closed, the period shall expire the next working day after the weekend or holiday.
Calculating Time. If anything is permitted or required to be done:
(a) a number of days or Business Days before a specified date, the date by which that thing may or must be done is to be calculated excluding the specified date; Example: if the Settlement Date falls on a Friday, 2 days before the as given:
(a) 5 Business Days after posting;
(b) if sent by facsimile, at the time indicated on a clear transmission report; and
(c) if sent by email, at the time it is sent.
Calculating Time. Unless otherwise stated, all references to “day” or “days” shall mean calendar days. If any time period set forth in this Agreement expires on other than a Business Day, such period shall be extended to and through the next succeeding Business Day.