Calculation of Transmission Congestion Credits Sample Clauses

Calculation of Transmission Congestion Credits. The total of all the target allocations determined as specified above shall be compared to the total Transmission Congestion Charges in each hour. If the total of the target allocations is less than the total of the Transmission Congestion Charges, the Transmission Congestion Credit for each Network Service User and Transmission Customer shall be equal to its target allocation. All remaining Transmission Congestion Charges shall be distributed as described below in Section 5.2.6 "
AutoNDA by SimpleDocs
Calculation of Transmission Congestion Credits. (b) If the total of the Target Allocations is greater than the total Transmission Congestion Charges for the hour resulting from both the Day-ahead Energy Market and the Real-time Energy Market, each FTR Hholder of Financial Transmission Rights shall be assigned a share of the total Transmission Congestion Charges in proportion to its Target Allocations for Financial Transmission Rights which have a positive Target Allocation value. Financial Transmission Rights which have a negative Target Allocation value are assigned the full Target Allocation value as a negative Transmission Congestion Credit. (c) At the end of a Planning Period if all FTR Hholders did not receive Transmission Congestion Credits equal to their Target Allocations, the Office of the Interconnection shall assess a charge equal to the difference between the Transmission Congestion Credit Target Allocations for all revenue deficient FTRs and the actual Transmission Congestion Credits allocated to those FTR Hholders. A charge assessed pursuant to this section shall also include any aggregate charge assessed pursuant to section 7.4.4(c) of Schedule 1 of this Agreement and shall be allocated to all FTR Hholders on a pro-rata basis according to the total Target Allocations for all FTRs held at any time during the relevant Planning Period. The charge shall be
Calculation of Transmission Congestion Credits. (a) The total of all the positive Target Allocations determined as specified above shall be compared to the Day-ahead Energy Market Transmission Congestion Charges in each hour. If the total of the Target Allocations is less than or equal to the total of the Day-ahead Energy Market Transmission Congestion Charges, the Transmission Congestion Credit for each entity holding an FTR shall be equal to its Target Allocation. All remaining Day-ahead Energy Market Transmission Congestion Charges shall be distributed as described below in Operating Agreement, Schedule 1, section 5.2.6 “Distribution of Excess Congestion Charges.” (b) If the total of the Target Allocations is greater than the Day-ahead Energy Market Transmission Congestion Charges for the hour, each FTR Holder shall be assigned a share of the Day-ahead Energy Market Transmission Congestion Charges in proportion to its Target Allocations for Financial Transmission Rights which have a positive Target Allocation value. Financial Transmission Rights which have a negative Target Allocation value are assigned the full Target Allocation value as a negative Transmission Congestion Credit. (c) At the end of a Planning Period if all FTR Holders did not receive Transmission Congestion Credits equal to their Target Allocations, the Office of the Interconnection shall assess a charge equal to the difference between the Transmission Congestion Credit Target Allocations for all revenue deficient FTRs and the actual Transmission Congestion Credits allocated to those FTR Holders. A charge assessed pursuant to this section shall also include any aggregate charge assessed pursuant to Operating Agreement, Schedule 1, section 7.4.4(c) and shall be allocated to all FTR Holders on a pro-rata basis according to the total Target Allocations for all FTRs held at any time during the relevant Planning Period. The charge shall be calculated and allocated in accordance with the following methodology: 1. The Office of the Interconnection shall calculate the total amount of uplift required as {[sum of the total monthly deficiencies in FTR Target Allocations for the Planning Period + the sum of the ARR Target Allocation deficiencies determined pursuant to Operating Agreement, Schedule 1, section 7.4.4(c)] – [sum of the total monthly excess ARR revenues and excess Day-ahead Energy Market Transmission Congestion Charges for the Planning Period]}. 2. For each Market Participant that held an FTR during the Planning Period, the Office of...

Related to Calculation of Transmission Congestion Credits

  • SUBMISSION OF THE MONTHLY MI REPORT 4.1 The completed MI Report shall be completed electronically and returned to the Authority by uploading the electronic MI Report computer file to MISO in accordance with the instructions provided in MISO. 4.2 The Authority reserves the right (acting reasonably) to specify that the MI Report be submitted by the Supplier using an alternative communication to that specified in paragraph 4.1 above such as email. The Supplier agrees to comply with any such instructions provided they do not materially increase the burden on the Supplier.

  • What Forms of Distribution Are Available from a Xxxxxxxxx Education Savings Account Distributions may be made as a lump sum of the entire account, or distributions of a portion of the account may be made as requested.

  • Disposal of Transmitted Items Upon your receipt of a confirmation approval from Credit Union that we have received an image that you have transmitted, you agree to retain the check for at least 60 calendar days from the date of the image transmission. After 60 days, you agree to destroy the check that you transmitted as an image, mark it "VOID", or otherwise render it incapable of further transmission, deposit, or presentment. During the time the retained check is available, you agree to promptly provide it to Credit Union upon request.

  • Distribution of UDP and TCP queries DNS probes will send UDP or TCP “DNS test” approximating the distribution of these queries.

  • Determination of Pass-Through Rates for LIBOR Certificates (a) On each Interest Determination Date so long as any LIBOR Certificates are outstanding, the Trustee will determine LIBOR on the basis of the British Bankers' Association ("BBA") "Interest Settlement Rate" for one-month deposits in U.S. dollars as found on Telerate page 3750 as of 11:00 a.m. London time on each LIBOR Determination Date. "Telerate Page 3750" means the display page currently so designated on the Moneyline Telerate Service (formerly the Dow Jones Markets) (or such other pagx xx may replace that page on that service for the purpose of displaying comparable rates or prices).

  • Determination of Pass-Through Rates for COFI Certificates The Pass-Through Rate for each Class of COFI Certificates for each Interest Accrual Period after the initial Interest Accrual Period shall be determined by the Trustee as provided below on the basis of the Index and the applicable formulae appearing in footnotes corresponding to the COFI Certificates in the table relating to the Certificates in the Preliminary Statement. Except as provided below, with respect to each Interest Accrual Period following the initial Interest Accrual Period, the Trustee shall not later than two Business Days prior to such Interest Accrual Period but following the publication of the applicable Index determine the Pass-Through Rate at which interest shall accrue in respect of the COFI Certificates during the related Interest Accrual Period. Except as provided below, the Index to be used in determining the respective Pass-Through Rates for the COFI Certificates for a particular Interest Accrual Period shall be COFI for the second calendar month preceding the Outside Reference Date for such Interest Accrual Period. If at the Outside Reference Date for any Interest Accrual Period, COFI for the second calendar month preceding such Outside Reference Date has not been published, the Trustee shall use COFI for the third calendar month preceding such Outside Reference Date. If COFI for neither the second nor third calendar months preceding any Outside Reference Date has been published on or before the related Outside Reference Date, the Index for such Interest Accrual Period and for all subsequent Interest Accrual Periods shall be the National Cost of Funds Index for the third calendar month preceding such Interest Accrual Period (or the fourth preceding calendar month if such National Cost of Funds Index for the third preceding calendar month has not been published by such Outside Reference Date). In the event that the National Cost of Funds Index for neither the third nor fourth calendar months preceding an Interest Accrual Period has been published on or before the related Outside Reference Date, then for such Interest Accrual Period and for each succeeding Interest Accrual Period, the Index shall be LIBOR, determined in the manner set forth below. With respect to any Interest Accrual Period for which the applicable Index is LIBOR, LIBOR for such Interest Accrual Period will be established by the Trustee on the related Interest Determination Date as provided in Section 4.08. In determining LIBOR and any Pass-Through Rate for the COFI Certificates or any Reserve Interest Rate, the Trustee may conclusively rely and shall be protected in relying upon the offered quotations (whether written, oral or on the Reuters Screen) from the Reference Banks or the New York City banks as to LIBOR or the Reserve Interest Rate, as appropriate, in effect from time to time. The Trustee shall not have any liability or responsibility to any Person for (i) the Trustee's selection of New York City banks for purposes of determining any Reserve Interest Rate or (ii) its inability, following a good-faith reasonable effort, to obtain such quotations from the Reference Banks or the New York City banks or to determine such arithmetic mean, all as provided for in this Section 4.07. The establishment of LIBOR and each Pass-Through Rate for the COFI Certificates by the Trustee shall (in the absence of manifest error) be final, conclusive and binding upon each Holder of a Certificate and the Trustee.

  • Dollar Limits Per Service Agreement Cost to diagnose, repair and/or replace - Per covered appliance $3,000

  • Transmission Delivery Service Implications Under ER Interconnection Service, Interconnection Customer will be eligible to inject power from the Generating Facility into and deliver power across the Transmission System on an “as available” basis up to the amount of MW identified in the applicable stability and steady state studies to the extent the upgrades initially required to qualify for ER Interconnection Service have been constructed. After that date FERC makes effective MISO’s Energy Market Tariff filed in Docket No. ER04-691-000, Interconnection Customer may place a bid to sell into the market up to the maximum identified Generating Facility output, subject to any conditions specified in the Interconnection Service approval, and the Generating Facility will be dispatched to the extent the Interconnection Customer’s bid clears. In all other instances, no transmission or other delivery service from the Generating Facility is assured, but Interconnection Customer may obtain Point-To-Point Transmission Service, Network Integration Transmission Service or be used for secondary network transmission service, pursuant to the Tariff, up to the maximum output identified in the stability and steady state studies. In those instances, in order for Interconnection Customer to obtain the right to deliver or inject energy beyond the Point of Interconnection or to improve its ability to do so, transmission delivery service must be obtained pursuant to the provisions of the Tariff. The Interconnection Customer’s ability to inject its Generating Facility output beyond the Point of Interconnection, therefore, will depend on the existing capacity of the Transmission or Distribution System as applicable, at such time as a Transmission Service request is made that would accommodate such delivery. The provision of Firm Point-To-Point Transmission Service or Network Integration Transmission Service may require the construction of additional Network or Distribution Upgrades.

  • BANK’S RECORD OF TRANSACTIONS The Bank’s record of transactions in respect of and in connection with the use and operation of TBS is conclusive and binding on the Account Holder for all purposes whatsoever save for any manifest error or clerical error but nothing herein shall preclude the Bank from rectifying at any time any error, irregularity or omission therein.

  • Rollovers of Settlement Payments From Bankrupt Airlines If you are a qualified airline employee who has received a qualified airline settlement payment from a commercial airline carrier under the approval of an order of a federal bankruptcy court in a case filed after September 11, 2001, and before January 1, 2007, you are allowed to roll over any portion of the proceeds into your Xxxx XXX within 180 days after receipt of such amount, or by a later date if extended by federal law. For further detailed information and effective dates you may obtain IRS Publication 590-A, Contributions to Individual Retirement Arrangements (IRAs), from the IRS or refer to the IRS website at xxx.xxx.xxx.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!