Capacity limit. 4.2.1 The Customer shall not take electricity through the Connection Point exceeding the Maximum Import Capacity or transmit electricity through the Connection Point exceeding the Maximum Export Capacity without the consent of the Company. 4.2.2 If the Maximum Import Capacity or the Maximum Export Capacity is exceeded without consent, the Company may give notice to the Customer setting out details and requesting the Customer to remedy the situation within twenty (20) Business Days of receipt of the notice, failing which the Company reserves the right to De-Energise and shall not re-Energise until such time as the Customer satisfies the Company that the Maximum Import Capacity or the Maximum Export Capacity (as applicable) will not be exceeded when the connection is renewed or arrangements have been made for an alteration or modification of the Connection Agreement.
Appears in 4 contracts
Samples: Transmission Connection Agreement, Transmission Connection Agreement, Transmission Connection Agreement
Capacity limit. 4.2.1 The Customer shall not take electricity through the Connection Point exceeding the Maximum Import Capacity or transmit electricity through the Connection Point exceeding the Maximum Export Capacity without the prior written consent of the Company.
4.2.2 If the Maximum Import Capacity or the Maximum Export Capacity is exceeded without consentexceeded, the Company may give notice to the Customer setting out details and requesting the Customer to remedy the situation within twenty (20) Business Days of receipt of the notice, failing which the Company reserves the right to De-Energise and shall not re-Energise until such time as the Customer satisfies the Company that the Maximum Import Capacity or the Maximum Export Capacity (as applicable) will not be exceeded when the connection is renewed or arrangements have been made for an alteration or modification of the Connection Agreement.
Appears in 2 contracts
Samples: Transmission Connection Agreement, Transmission Connection Agreement
Capacity limit. Deleted: prior written
4.2.1 The Customer shall not take electricity through the Connection Point exceeding the Maximum Import Capacity or transmit electricity through the Connection Point exceeding the Maximum Export Capacity without the consent of the Company.
4.2.2 If the Maximum Import Capacity or the Maximum Export Capacity is exceeded without consent, the Company may give notice to the Customer setting out details and requesting the Customer to remedy the situation within twenty (20) Business Days of receipt of the notice, failing which the Company reserves the right to De-Energise and shall not re-Energise until such time as the Customer satisfies the Company that the Maximum Import Capacity or the Maximum Export Capacity (as applicable) will not be exceeded when the connection is renewed or arrangements have been made for an alteration or modification of the Connection Agreement.
Appears in 1 contract
Samples: Transmission Connection Agreement
Capacity limit. 4.2.1 The Customer shall not take electricity through the Connection Point exceeding the Maximum Import Capacity or transmit electricity through the Connection Point exceeding the Maximum Export Capacity without the prior written consent of the Company.
4.2.2 If the Maximum Import Capacity or the Maximum Export Capacity is exceeded without consent, the Company may give notice to the Customer setting out details and requesting the Customer to remedy the situation within twenty (20) Business Days of receipt of the notice, failing which the Company reserves the right to De-Energise and shall not re-Energise until such time as the Customer satisfies the Company that the Maximum Import Capacity or the Maximum Export Capacity (as applicable) will not be exceeded when the connection is renewed or arrangements have been made for an alteration or modification of the Connection Agreement.
Appears in 1 contract
Samples: Transmission Connection Agreement