Certain Claims Excluded from General Claims. All claims for Unavoidable Delay as defined in Article 3.5.8 must be filed and processed pursuant to Article 3.5.10 and are subject to the limitations of Articles 3.5.7 and 3.5.9 All claims concerning designation of a Sole Source must be filed and processed pursuant to Articles 2.2.4 or 3.4.6 and are subject to the provisions and limitations therein.
Appears in 10 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Certain Claims Excluded from General Claims. All claims for Unavoidable Delay as defined in Article 3.5.8 Section 3.3.8 must be filed and processed pursuant to Article 3.5.10 Section 3.3.10 and are subject to the limitations of Articles 3.5.7 Sections 3.3.7 and 3.5.9 All claims concerning designation of a Sole Source must be filed and processed pursuant to Articles 2.2.4 or 3.4.6 and are subject to the provisions and limitations therein.3.3.9
Appears in 1 contract
Certain Claims Excluded from General Claims. All claims for Unavoidable Delay as defined in Article Section 3.5.8 must be filed and processed pursuant to Article Section 3.5.10 and are subject to the limitations of Articles Sections 3.5.7 and 3.5.9 All claims concerning designation of a Sole Source must be filed and processed pursuant to Articles 2.2.4 or 3.4.6 and are subject to the provisions and limitations therein.3.5.9
Appears in 1 contract
Samples: Construction Management Agreement