Common use of Cessation of Work and Removal of Contractor's Equipment Clause in Contracts

Cessation of Work and Removal of Contractor's Equipment. After a notice of termination under Sub-Clause 15.5 [Contract Awarder's Entitlement to Termination], Sub-Clause 16.2 [Termination by Contractor] or Sub-Clause 19.6 [Optional Termination, Payment and Release] has taken effect, the Contractor shall promptly: (a) cease all further work, except for such work as may have been instructed by the Contract Awarder for the protection of life or property or for the safety of the Works, (b) hand over Contractor's Documents, Plant, Materials and other work, for which the Contractor has received payment, and (c) remove all other Goods from the Work Site, except as necessary for safety, and leave the Work Site.

Appears in 2 contracts

Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)

AutoNDA by SimpleDocs

Cessation of Work and Removal of Contractor's Equipment. After a notice of termination under Sub-Clause 15.5 [Contract Awarder's Employer’s Entitlement to Termination], Sub-Clause 16.2 [Termination by Contractor] or Sub-Clause 19.6 [Optional Termination, Payment and Release] has taken effect, the Contractor shall promptly: (a) cease all further work, except for such work as may have been instructed by the Contract Awarder Engineer for the protection of life or property or for the safety of the Works, (b) hand over Contractor's Documents, Plant, Materials and other work, for which the Contractor has received payment, and (c) remove all other Goods from the Work Site, except as necessary for safety, and leave the Work Site.

Appears in 1 contract

Samples: Contract Agreement

AutoNDA by SimpleDocs

Cessation of Work and Removal of Contractor's Equipment. After a notice of termination under Sub-Clause 15.5 [Contract Awarder's Employer’s Entitlement to TerminationTermination for Convenience], Sub-Clause 16.2 [Termination by Contractor] or Sub-Clause 19.6 [Optional Termination, Payment and Release] has taken effect, the Contractor shall promptly: (a) cease all further work, except for such work as may have been instructed by the Contract Awarder Engineer for the protection of life or property or for the safety of the Works, (b) hand over Contractor's ’s Documents, Plant, Materials and other work, for which the Contractor has received payment, and (c) remove all other Goods from the Work Site, except as necessary for safety, and leave the Work Site.

Appears in 1 contract

Samples: Unit Price Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!