PROTECTION OF WORK AND PROPERTY. Contractor shall erect and properly maintain at all times, as required by conditions and progress of the Work, all necessary safeguards, signs, barriers, lights, and security persons for protection of workers and the public, and shall post danger signs warning against hazards created by the Work. In an emergency affecting life and safety of life or of Work or of adjoining property, Contractor, without special instruction or authorization from District, is permitted to act at his discretion to prevent such threatened loss or injury.
PROTECTION OF WORK AND PROPERTY. (a) Project Co shall protect the Work and the Owner’s property at the Site, including the Existing Facility and property adjacent to the Site, from damage which may arise as a result of Project Co’s operations under this Project Agreement, and shall be responsible for such damage, except damage which occurs as a result of:
(i) Design Issues (other than Design Issues which are properly characterized as a Project Co Design Issues under Section 11.17); or
(ii) acts or omissions by Owner, the Consultant or any contractor retained by Owner directly and whose contract is not assigned to Project Co, their respective agents and employees.
(b) Should Project Co, in the performance of this Project Agreement, damage the Work, the Owner’s property at the Site, including the Existing Facility or property adjacent to the Site, Project Co shall be responsible to Make Good such damage at Project Co’s expense.
(c) Should damage occur to the Work or Owner’s property at the Site, including the Existing Facility for which Project Co is not responsible, as provided in Section 11.21(a), Project Co shall Make Good such damage to the Work and, if Owner so directs, to the Owner’s property and the Guaranteed Price and Contract Time shall be adjusted (including on account of the Overhead and Profit Fee) as provided in Schedule 11 – Change Procedure.
(d) Project Co shall not undertake to repair and/or replace any damage whatsoever to adjoining property or acknowledge the same was caused or occasioned by Project Co, without first consulting Owner and receiving written instructions as to the course of action to be followed.
(e) Notwithstanding Section 11.21(d), where there is danger to life or property which arises out of or in connection with the performance of the Work, either Party may, but Project Co shall, take such emergency action as is necessary to remove the danger.
(f) If any Project Co Party has caused damage to the work of another contractor related to the Project, Project Co agrees upon due notice to settle with the other contractor by negotiation or arbitration in accordance with Section 11.19(e) and Schedule 14 – Dispute Resolution Procedure. If the other contractor makes a claim against Owner on account of damage alleged to have been so sustained, the dispute shall be dealt with in substantially the same manner as contemplated in Section 11.19(e) and Schedule 14 – Dispute Resolution Procedure.
PROTECTION OF WORK AND PROPERTY a. The Contractor shall be responsible for each operation and all work on the Project, both permanent and temporary. The Contractor shall protect the work and materials from damage due to negligence, the action of the elements, the carelessness of third parties, vandalism, or any other cause whatsoever, until the final completion and acceptance of the Project. Should improper work by the Contractor be covered by another contractor and damage or defects result, the whole work affected shall be made good by the Contractor to the satisfaction of the Project Manager and District without expense to the District. The Contractor shall take reasonable care to avoid damage to existing facilities or utilities, whether on the Project or adjacent to it, and Contractor shall be liable for any damage thereto or interruption of service due to Contractor’s operations. If the Contractor encounters any facilities or utilities not shown on the drawings or not reasonably inferable therefrom, Contractor shall promptly notify the Project Manager about them, and shall do no further work which may cause damage to same. If it is determined that some action needs to be taken regarding facilities not shown, the Contractor will be given directives on what action to take, and any additional cost to the Contractor incurred thereby will be handled by Change Order.
b. The property limits of the area of the Project are indicated on the drawings. Except for work specifically shown or noted, Contractor shall confine Contractor’s operations within the indicated property limits. The Contractor shall provide, install, and maintain all shoring, bracing and underpinning necessary to support adjacent property, streets, buildings and structures, that may be affected by building operations for this work; shall serve or cause to be served all legal notices to adjoining property owners that may be necessary for their protection; and shall protect from damage all adjacent buildings, fences, landscaping, and repair or replace any such property damaged in the course of work under the Contract.
PROTECTION OF WORK AND PROPERTY. Contractor shall continuously maintain adequate protection of Work from damage and shall protect the District’s property at all times from injury or loss arising in connection with the Contract. Contractor shall make good at its own expense any such damage, injury or loss that may result from its effort in connection with the Work. Contractor shall provide all facilities for protection required by public authority or local conditions.
PROTECTION OF WORK AND PROPERTY. 4.1.1 The Contractor shall protect the Work, Persons and the Owner’s property and property adjacent to, in the vicinity of or proximate to the Site from damage which may arise as the result of the Work (including from settlement of ground, flow of water, vibration or shock), and the Contractor shall, and shall cause the other Contractor Parties to, take all precautions to avoid such damage. The Contractor shall be responsible for making good any such damage, at its cost, except damage which occurs as the result of: .1 subject to 3.6 – DOCUMENT REVIEW, errors, inconsistencies or omissions in the Agreement; and .2 negligent acts or omissions by the Owner, the Owner Representative, the Contract Administrator, any other contractors (other than the Contractor Parties), and their respective Personnel.
4.1.2 Should damage occur to the Work or Owner’s property for which the Contractor is not responsible for pursuant to the Agreement, the Contractor shall make good such damage to the Work and, if the Owner so directs, to the Owner’s property. The Contract Price and Contract Time shall be adjusted as provided in 7.1 - OWNER’S RIGHT TO MAKE CHANGES, 7.2 - CHANGE ORDER and 7.3 - CHANGE DIRECTIVE.
PROTECTION OF WORK AND PROPERTY. Provider and all of its subcontractors shall maintain at all times, as required by conditions and progress of work, all necessary safeguards for the protection of employees and the public. In an emergency affecting life and safety of life or work or of adjoining property, Provider is permitted, without special instruction or authorization from the District, to act at its discretion to prevent such threatened loss or injury.
PROTECTION OF WORK AND PROPERTY. The Contractor shall be responsible for all damages to persons or property that occur as a result of his fault or negligence in connection with the prosecution of this contract and shall be responsible for the proper care and protection of all materials delivered and work performed until completion and final acceptance by the District. All work shall be solely at the Contractor’s risk. Contractor shall adequately protect adjacent property from settlement or loss of lateral support as provided by law and contract documents. Contractor shall take all necessary precautions for safety of employees on the work and shall comply with all applicable safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to premises where work is being performed. Contractor shall erect and properly maintain at all times, as required by conditions and progress of work, all necessary safeguards, signs, barriers, light and watchmen for protection of workers and the public and shall post danger signs warning against hazards created by such features in the course of construction. Contractor shall designate a responsible member of the organization on the work, whose duty shall be prevention of accidents. Contractor shall report name and position of person so designated to District. In an emergency affecting life and safety of life or of work or of adjoining property, Contractor, without special instruction or authorization from District, is permitted to act at its discretion to prevent the threatened loss or injury. It shall be the responsibility of the Contractor to ascertain from the District the rules and regulations pertaining to safety, security and driving on school grounds, particularly when children are present
PROTECTION OF WORK AND PROPERTY. Contractor shall continuously maintain adequate protection of his work and materials, protect the property on which the Project is to be constructed from injury or loss arising in connection with the Contract and adequately protect adjacent property as provided by law and Contract Documents. Contractor shall at all times conduct his work so as to assure the least possible obstruction to traffic and adjacent residents. The safety and the protection of persons and property of the general public and residents along the street, highway and areas adjacent to the work shall be provided for by Contractor. Contractor shall make good any damage, injury or loss, except such as may be:
a. directly due to errors in the Contract Documents;
b. caused by agents or employees of County; or
c. due to causes beyond Contractor's control and not due to his fault or negligence. Contractor shall take all necessary precautions for the safety of employees on the work and shall comply with all applicable provisions of federal, state, municipal, county or any other political subdivision's safety laws and building codes to prevent accident or injury to persons on, about or adjacent to the premises where the work is being performed. He shall erect and properly maintain at all times, as required by the conditions and progress of the work, all necessary safeguards for the protection of workers and the public and shall take all other action necessary to assure the safe passage of pedestrians and automobiles.
PROTECTION OF WORK AND PROPERTY. The Construction Manager shall protect the Work and the Owner’s property and property adjacent to the Place of the Work from damage which may arise as the result of the Construction Manager’s operations under this Contract, and shall be responsible for such damage, except damage which occurs as the result of:
PROTECTION OF WORK AND PROPERTY. Contractor shall be responsible for all damages to persons or property that occur as a result of Contractor’s fault or negligence in connection with the prosecution of this Contract and shall be responsible for the proper care and protection of all materials delivered and work performed until completion and final acceptance by District.