Common use of Change of Contract Times Clause in Contracts

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written Amendment. Any Claim for an adjustment in the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim to the ENGINEER and the other party to the Contract in accordance with the provisions of paragraph 10.05.

Appears in 6 contracts

Samples: Agreement, Agreement, Agreement

AutoNDA by SimpleDocs

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written Amendment. Any Claim for an adjustment in the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim to the ENGINEER Owner’s Representative and the other party to the Contract in accordance with the provisions of paragraph 10.05.

Appears in 2 contracts

Samples: www.westchestermedicalcenter.org, www.westchestermedicalcenter.org

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim Claim to the ENGINEER Engineer and the other party to the Contract in accordance with the provisions of paragraph Paragraph 10.05.

Appears in 1 contract

Samples: www.cityofbelpre.com

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in of the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim pursuant to the ENGINEER and the other party to the Contract in accordance with the provisions of paragraph 10.05.9.3.A.

Appears in 1 contract

Samples: Agreement

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim to the ENGINEER and the other party to the Contract in accordance with the provisions of paragraph Paragraph 10.05.

Appears in 1 contract

Samples: Agreement

AutoNDA by SimpleDocs

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in of the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim pursuant to the ENGINEER and the other party to the Contract in accordance with the provisions of paragraph 10.05.9.03.A.

Appears in 1 contract

Samples: Nova Oil Inc

Change of Contract Times. A. The Contract Times (or Milestones) may only be changed by a Change Order or by a Written AmendmentOrder. Any Claim for an adjustment in the Contract Times (or Milestones) shall be based on written notice submitted by the party making the claim Claim to the ENGINEER Architect and the other party to the Contract in accordance with the provisions of paragraph Paragraph 10.05.

Appears in 1 contract

Samples: Construction Manager at Risk Agreement