Common use of CHANGES IN RULES AND REGULATIONS Clause in Contracts

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, first agree to: (i) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (ii) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iii) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacity; (iv) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speed; and (v) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Such agreement between the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 10 contracts

Samples: Shipbuilding Contract (DHT Holdings, Inc.), Shipbuilding Contract (DHT Holdings, Inc.), Shipbuilding Contract (DHT Holdings, Inc.)

AutoNDA by SimpleDocs

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If any requirements as to CLASSIFICATION SOCIETY or as to the specified rules and regulations with which the construction of the VESSEL is required to comply in Article I. 3. (a) are altered or changed by the CLASSIFICATION SOCIETY or other regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) working days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the guaranteed speed requirements if such compliance results in any increase or reduction in the speed; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 6 contracts

Samples: Shipbuilding Contract (Gener8 Maritime, Inc.), Shipbuilding Contract (Gener8 Maritime, Inc.), Shipbuilding Contract (Gener8 Maritime, Inc.)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten fifteen (1015) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree toto : (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliancecompliance ; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliancecompliance ; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speedspeed ; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 5 contracts

Samples: Shipbuilding Contract (Danaos Corp), Shipbuilding Contract (Danaos Corp), Shipbuilding Contract (Danaos Corp)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days days, or such longer period as is commercially reasonable in the circumstances by the agreement of the parties acting reasonably after giving the notice to the BUILDER or receiving the notice on the adjustment due to such alterations or changes from the BUILDER, the BUYER shall advise the BUILDER of its decision as to the alterations and changes, if any, changes to be made on the VESSEL which the BUYER, in its sole discretion, shall decideVESSEL. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree toto reasonable adjustment on: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacity; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speed; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACTSPECIFICATIONS.

Appears in 3 contracts

Samples: Shipbuilding Contract (Seaspan CORP), Shipbuilding Contract (Seaspan CORP), Shipbuilding Contract (Seaspan CORP)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speedspeed ; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER'S delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 3 contracts

Samples: Shipbuilding Contract (International Shipholding Corp), Shipbuilding Contract (International Shipholding Corp), Shipbuilding Contract (International Shipholding Corp)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speedspeed ; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 2 contracts

Samples: Shipbuilding Contract (Gener8 Maritime, Inc.), Shipbuilding Contract (Gener8 Maritime, Inc.)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten twenty one (1021) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned necessary due to by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned necessary due to by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacity; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speed; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN PLANS or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by The BUILDER shall assist to the parties best of its efforts to reach such agreement shall be referred minimize the consequence hereof to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.. (End of Article)

Appears in 2 contracts

Samples: Shipbuilding Contract (Capital Maritime & Trading Corp.), Shipbuilding Contract (Capital Maritime & Trading Corp.)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days days, or such longer period as is commercially reasonable in the circumstances by the agreement of the parties acting reasonably after giving the notice to the BUILDER or receiving the notice on the adjustment due to such alterations or changes from the BUILDER, the BUYER shall advise the BUILDER of its decision as to the alterations and changes, if any, changes to be made on the VESSEL which the BUYER, in its sole discretion, shall decideVESSEL. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree toto reasonable adjustment on: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliancecompliance ; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliancecompliance ; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speedspeed ; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACTSPECIFICATIONS.

Appears in 1 contract

Samples: Shipbuilding Contract (Seaspan CORP)

AutoNDA by SimpleDocs

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised to make such alterations or changes, or there are any new rules or regulations coming into force that changes after the VESSEL is required to comply withCONTRACT date, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) , The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree toto : (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliancecompliance ; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliancecompliance ; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speedspeed ; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 1 contract

Samples: Shipbuilding Contract (Knightsbridge Tankers LTD)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing execution of this CONTRACT, the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or other regulatory bodies authorised to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereofNOTICE thereof or becoming aware of such changes, shall forthwith give notice NOTICE thereof to the other party in writing. Thereupon, within ten (10) days after giving or receiving the notice NOTICE, the BUILDER shall give NOTICE to the BUYER specifying (i) the costs and expenses to be reimbursed by the BUYER to the BUILDER in complying with the altered or receiving changed rules and regulations and (ii) the notice proposed new Delivery Date, if adjustment of Delivery Date is necessary in complying with the altered or changed rules and regulations. Thereupon, within ten (10) Business Days after the BUYER’s receipt of such NOTICE from the BUILDER, the BUYER shall advise give NOTICE to the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or or changes if the BUYER fails to notify give NOTICE to the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided BUYER on condition that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (i) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (ii) any reasonable extension or advancement in the Delivery Date of the VESSEL DELIVERY DATE that is occasioned by such compliance; (iii) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacity; (iv) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speed; and (v) any other reasonable alterations in the terms of this CONTRACT or of and the SPECIFICATIONS or the PLAN or bothSPECIFICATIONS, if such compliance makes such alterations of the terms necessary. (b) If the parties are unable to agree any of the above within fourteen (14) days, the parties shall by mutual agreement refer the dispute to a third party expert as may be mutually agreed between the parties hereto and who shall act as an expert and not as an arbitrator and whose decision shall be final, conclusive and binding on the parties hereto. If the parties are unable to agree on an expert within seven (7) days, the BUILDER shall appoint a qualified expert subject to the BUYER’s approval and such approval shall not be unreasonably withheld by the BUYER. The appointed expert must make a final, conclusive and binding decision within seven (7) days from his/her appointment. In the event that the for any reason the technical expert is unable to make a final, conclusive and binding decision in accordance with the foregoing or the event that either party makes an election the matters hereunder shall be referred to determination in accordance with Article XIII. Any delay in the construction of the VESSEL caused by the Parties in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction (End of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.ARTICLE V)

Appears in 1 contract

Samples: Shipbuilding Contract (Scorpio Bulkers Inc.)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speed; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’S delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 1 contract

Samples: Shipbuilding Contract (Gener8 Maritime, Inc.)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, BUILDER the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree to: (ia) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (iib) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iiic) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacitycapacity ; (ivd) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speedspeed ; and (ve) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between by the BUYER and the BUILDER shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 1 contract

Samples: Shipbuilding Contract (Gener8 Maritime, Inc.)

CHANGES IN RULES AND REGULATIONS. (a) If, after the date of signing of this CONTRACT, If the specified rules and regulations with which the construction of the VESSEL is required to comply are altered or changed by the CLASSIFICATION SOCIETY or regulatory bodies authorised authorized to make such alterations or changes, or there are any new rules or regulations coming into force that the VESSEL is required to comply with, either the BUYER or the BUILDER, upon receipt of due notice thereof, shall forthwith give notice thereof to the other party in writing. Thereupon, within ten (10) days after giving the notice to the BUILDER or receiving the notice from the BUILDER, the BUYER shall advise the BUILDER as to the alterations and changes, if any, to be made on the VESSEL which the BUYER, in its sole discretion, shall decide. The BUILDER shall not be obliged to comply with such alterations and/or changes if the BUYER fails to notify the BUILDER of its decision within the time limit stated above. (b) . The BUILDER shall comply promptly with the said request of the BUYER, provided that the BUILDER and the BUYER shall, acting reasonably, shall first agree toupon: (i) any reasonable increase or decrease in the CONTRACT PRICE of the VESSEL that is occasioned by such compliance; (ii) any reasonable extension or advancement in the Delivery Date of the VESSEL that is occasioned by such compliance; (iii) any reasonable increase or decrease in the deadweight and/or cubic capacity of the VESSEL, if such compliance results in any increase or reduction in the deadweight and/or cubic capacity; (iv) any reasonable adjustment of the speed requirements if such compliance results in any increase or reduction in the speed; speed and (v) any other reasonable alterations in the terms of this CONTRACT or of the SPECIFICATIONS or the PLAN or both, if such compliance makes such alterations of the terms necessary. Any delay in the construction of the VESSEL caused by the BUYER’s delay in making a decision or agreement as above shall constitute a permissible delay under this CONTRACT. Such agreement between on the BUYER and the BUILDER matters set out above shall be effected in the same manner as provided above for modification and change of the SPECIFICATIONS and the PLAN. Any failure by the parties to reach such agreement shall be referred to arbitration in accordance with Article XIII hereof. Any delay in the construction of the VESSEL caused by the BUYER's delay in making a decision or by reaching an agreement as above, shall constitute a permissible delay under this CONTRACT.

Appears in 1 contract

Samples: Shipbuilding Contract (Tsakos Energy Navigation LTD)