Common use of Changes Requested by Contractor Clause in Contracts

Changes Requested by Contractor. With respect to any matter that may involve or require an adjustment to the Contract Time or the Contract Price, Contractor shall provide written notice of the underlying facts and circumstances that gave rise to the potential change within seven (7) days or prior to the alteration of conditions, whichever is earlier. Failure to give notice shall constitute a waiver of Contractor’s right to a change order. If any costs are not capable of being determined within seven (7) days, then Contractor shall request a Change Order within seven (7) days of when the costs are capable of being determined.

Appears in 6 contracts

Samples: Form Construction Contract, Form Construction Contract, Form Construction Contract