CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.
Appears in 26 contracts
Samples: Contract for Construction, Construction Contract, Contract for Construction
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes Design-Builder intends to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Workportion of the Work that relates to the Claim. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.
Appears in 25 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein in Section 15.1.3 shall be given before proceeding to execute the Workportion of the Work that is the subject of the Claim. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.
Appears in 11 contracts
Samples: Standard Form of Agreement Between Owner and Construction Manager as Constructor, Construction Contract, Standard Form of Agreement Between Owner and Construction Manager as Constructor
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Article 13.
Appears in 11 contracts
Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.6.
Appears in 5 contracts
Samples: Construction Manager at Risk Agreement, Construction Contract, Lease Agreement (Immunicon Corp)
CLAIMS FOR ADDITIONAL COST. If the Contractor Design-Builder wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4A.10.6.
Appears in 5 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
CLAIMS FOR ADDITIONAL COST. If the Contractor Construction Manager wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4property.
Appears in 5 contracts
Samples: Construction Management Services Agreement, Construction Management Services Agreement, Construction Management Services Agreement
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Article XXI.
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
CLAIMS FOR ADDITIONAL COST. be given be endangeri If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before fore proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering ng life or property arising under Section 10.4Article 13.
Appears in 3 contracts
Samples: Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project, Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4when the giving of such notice would increase the risk of injury or damage to persons or property.
Appears in 2 contracts
Samples: Owner Contractor Agreement, Owner Contractor Agreement
CLAIMS FOR ADDITIONAL COST. If the Contractor Construction Manager wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.5.
Appears in 2 contracts
Samples: Agreement Between Owner and Architect (Chukchansi Economic Development Authority), Construction Manager Agreement (Chukchansi Economic Development Authority)
CLAIMS FOR ADDITIONAL COST. If the Contractor Design Builder wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4property.
Appears in 2 contracts
Samples: Agreement for Design Build Services, Agreement for Continuing Design Build Services
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.6. Any change in the Contract Sum resulting from such Claim shall be authorized by written Modification.
Appears in 2 contracts
Samples: Services Agreement, Services Agreement
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Workwork and such Claim shall be made and prosecuted in accordance with the terms of this Agreement. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 11.3.
Appears in 1 contract
Samples: Guaranteed Maximum Price Construction Agreement (Gaylord Entertainment Co /De)
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as notic provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.Article 13. pro elay
Appears in 1 contract
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.property. If the Contractor believes additional cost is involved for reasons including but not limited to (1) a written interpretation from the ARCHITECT/ENGINEER, (2) an order by the Owner to stop the Work where the Contractor was not at fault,
Appears in 1 contract
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract SumGuaranteed Maximum Price, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.
Appears in 1 contract
Samples: Construction Contract (National Instruments Corp /De/)
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall notic be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency rela endangering life or property arising under Section 10.4.. pro elay
Appears in 1 contract
Samples: Construction Contract
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 18.4.
Appears in 1 contract
Samples: Construction Manager Agreement
CLAIMS FOR ADDITIONAL COST. If if the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.
Appears in 1 contract
Samples: Construction Contract (Digex Inc/De)
CLAIMS FOR ADDITIONAL COST. If the XXXX Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.Paragraph 10.6. XXXX Contractor shall, upon recognition of a condition giving rise to a claim for additional cost, establish
Appears in 1 contract
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as is provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.
Appears in 1 contract
Samples: Construction Contract (Monarch Casino & Resort Inc)
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.410.6.
Appears in 1 contract
Samples: Construction Contract (Sierra Pacific Resources /Nv/)
CLAIMS FOR ADDITIONAL COST. If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4Paragraph 10.
Appears in 1 contract