Common use of Claims for Additional Time Clause in Contracts

Claims for Additional Time. Any Claim by Contractor for an increase in the Contract Time shall be submitted in writing as required by the Contract Documents. The Contractor’s Claim shall include an estimate of the probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary. If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 3 contracts

Samples: Agreement, www.forms.procurement.wayne.edu, www.forms.procurement.wayne.edu

AutoNDA by SimpleDocs

Claims for Additional Time. Any If Contractor wishes to make a Claim by Contractor for an increase in the Contract Time Time, notice as provided in Subsection C above shall be submitted in writing as required by the Contract Documentsgiven. The Contractor’s Claim shall include an estimate of the cost and of probable effect of delay on progress of the Work. In the case of a continuing delay delay, only one Claim is necessary. If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and time, could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 2 contracts

Samples: Contract for Local Improvement, Agreement

Claims for Additional Time. Any If the Contractor wishes to make a Claim by Contractor for an increase increases in the Contract Time time to complete the Work, written notice as provided herein shall be submitted in writing as required by the Contract Documentsgiven. The Contractor’s Claim shall include an estimate of the probable effect of delay on progress of the Work. In the case of a continuing delay delay, only one Claim is necessary. If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Samples: Cherokee Nation Entertainment

Claims for Additional Time. Any § 15.1.5.1 If the Contractor wishes to make a Claim by Contractor for an increase in the Contract Time Time, written notice as provided herein shall be submitted in writing as required by the Contract Documentsgiven. The Contractor’s Claim shall include an estimate of the cost and of probable effect of delay on progress of the Work. In the case of a continuing delay delay, only one Claim is necessary. If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and time, could not have been reasonably anticipated, anticipated and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Samples: Indemnity Agreement

AutoNDA by SimpleDocs

Claims for Additional Time. Any If the Contractor wishes to make a Claim by Contractor for an increase increases in the Contract Time time to complete the Work, written notice as provided herein shall be submitted in writing as required by the Contract Documentsgiven. The Contractor’s Claim shall include an estimate of the probable probably effect of delay on progress of the Work. In the case of a continuing delay delay, only one Claim is necessary. If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction.

Appears in 1 contract

Samples: Subcontract Agreement