Claims for Additional Time. § 10.5.1 If the Contractor wishes to make a Claim for an increase in the Contract time, written notice shall be given to the Owner within 10 days of the event from which the Claim arises. The Claim shall include an explanation of the basis for the delay claim and an estimate of the probable effect of delay on progress of the Work.
Appears in 2 contracts
Samples: Abenaqui Pump Station Design/Build Contract, Interior Renovation Contract Town Hall Annex
Claims for Additional Time. § 10.5.1 4.3.7.1 If the Contractor wishes to make a Claim for an increase in the Contract timeTime, written notice as provided herein shall be given to received by the Owner within 10 seven (7) days of occurrence or discovery of the event from which the Claim ariseschange. The Contractor's Claim shall include an explanation of the basis for the delay claim and an estimate of the cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is 30 necessary.
Appears in 2 contracts
Samples: www.mohave.edu, cdn.maricopa.edu
Claims for Additional Time. § 10.5.1 4.3.8.1 If the Contractor wishes to make a Claim for an increase in the Contract timeTime, written notice as provided herein shall be given to the Owner within 10 days of the event from which the Claim arisesgiven. The Contractor's Claim shall include an explanation demonstrate that the task is on the critical path and identify the new completion date. In the case of the basis for the delay claim and an estimate of the probable effect of delay on progress of the Worka continuing delay, only one Claim is necessary.
Appears in 2 contracts
Samples: wtaw.com, Architectural Services Agreement
Claims for Additional Time. § 10.5.1 4.3.8.1 If the Contractor wishes to make a Claim for an increase in the Contract timeTime, written notice as provided herein shall be given to the Owner within 10 days of the event from which the Claim arisesgiven. The Contractor's Claim shall include an explanation of the basis for the delay claim and an estimate of the cost and of probable effect of delay on progress of the Work. in the case of a continuing delay only one Claim is necessary.
Appears in 1 contract
Samples: Agreement (Digex Inc/De)
Claims for Additional Time. § 10.5.1 4.3.7.1 If the Contractor wishes to make a Claim for an increase in the Contract timeTime, written notice as provided herein shall be given to 15 received by the Owner within 10 seven (7) days of occurrence or discovery of the event from which the Claim ariseschange. The Contractor's Claim shall include an explanation of the basis for the delay claim and an estimate of the cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary.
Appears in 1 contract
Samples: procurement.maricopa.edu
Claims for Additional Time. § 10.5.1 4.3.8.1 If the Contractor wishes to make a Claim claim for an increase in the Contract time, the Contractor shall give the Architect written notice shall be given to the Owner thereof within 10 seven (7) days after occurrence of the event from which the Claim arisesgiving rise to such claim. The Claim Contractor shall include an explanation have the burden of demonstrating the effect of the basis for the delay claim and an estimate of the probable effect of claimed delay on progress of the WorkContract Time, and shall furnish the Architect with such documentation relating thereto as the Architect may reasonably require.
Appears in 1 contract
Samples: www.spotsylvania.k12.va.us:443