Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary. .2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.
Appears in 2 contracts
Samples: Contract for Construction, Contract for Construction
Claims for Additional Time. .1 4.3.8.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In in the case of a continuing delay, delay only one Claim is necessary.
.2 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Construction Contract (Digex Inc/De)
Claims for Additional Time. .1 § 15.1.5.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on d progress of the Work. In the case of a continuing delay, only one Claim is necessary.
.2 § 15.1.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Construction Contract
Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on d progress of the Work. In the case of a continuing delay, only one Claim is necessary.
.2 . § 17.9.5.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.
Appears in 1 contract
Claims for Additional Time. .1 § 4.3.7.1 If the Contractor wishes to make a Claim for an increase in the applicable Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.
.2 § 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Construction Contract (Sierra Pacific Resources /Nv/)
Claims for Additional Time. .1 4.3.8.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s 's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.
.2 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Construction Contract (Digex Inc/De)
Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase increases in the Contract Timetime to complete the Work, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
.2 . If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Architectural Services Agreement
Claims for Additional Time. .1 If the Contractor wishes to make a Claim for an increase increases in the Contract Timetime to complete the Work, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable probably effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.
.2 . If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, time and could not have been reasonably anticipated anticipated, and that weather conditions had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Subcontract Agreement
Claims for Additional Time. .1 4.3.7.1 If the Contractor wishes to make a Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, delay only one Claim is necessary.
.2 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.
Appears in 1 contract
Samples: Construction Contract