Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4. 4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 16 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one seven (217) days after first observance of the conditions. Site conditions which an experienced and prudent contractor could have anticipated by visiting the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companies. The Engineer or Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's ’s cost of, or the required time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Engineer or Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Engineer or Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Engineer or Architect for initial determination, subject to further proceedings proceeding pursuant to Paragraph 4.4these Contract Documents.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 3 contracts
Samples: Trade Contractor Agreement, Trade Contractor Agreement, Trade Contractor Agreement
Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect ARCHITECT/ENGINEER will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect ARCHITECT/ENGINEER determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect ARCHITECT/ENGINEER shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect ARCHITECT/ENGINEER has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect ARCHITECT/ENGINEER for initial determination, subject to further proceedings pursuant to Paragraph 4.44.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 3 contracts
Samples: Architectural/Engineering Services Agreement, Continuing Service Contract, Architectural/Engineering Services Agreement
Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 2 contracts
Samples: Lease Agreement (Immunicon Corp), Standard Form of Agreement Between Owner and Contractor (Corixa Corp)
Claims for Concealed or Unknown Conditions. If conditions not reasonably discoverable by Construction Manager or the applicable Subcontractor are encountered at the site which are (1l) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one three (213) days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the ContractorConstruction Manager's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both, but not in the amount of Construction Manager's Fee. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents or that such differences were reasonably discoverable by Construction Manager or the applicable Subcontractor and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor Construction Manager in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one seven (217) days after the Architect has given notice of the decision. If Subject to Sections 1.1.3 and 3.2.4 hereof, if the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4the Agreement.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 2 contracts
Samples: Agreement Between Owner and Architect (Chukchansi Economic Development Authority), Construction Manager Agreement (Chukchansi Economic Development Authority)
Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or otherwise known to (or should have been known to) Contractor, or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, and should not have been known to Contractor, then written notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one fourteen (2114) days after first observance of the conditions. The Architect Owner will promptly investigate such conditions and, if they differ materially from what Contractor knew or should have known and cause an increase or decrease in the Contractor's ’s cost of, of or time required for, for performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents or that otherwise should have been known to Contractor, and that no change in the terms of the Contract is justified, the Architect Owner shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party Contractor in opposition to such determination must be made within twenty-one thirty (2130) days after the Architect Owner has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment determination shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.
4.3.5.1 No arbitration as provided herein. It is expressly agreed that no adjustment in the Contract Time or Contract Sum shall be permitted, however, permitted in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's ’s (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, testtests, reviews, reviews and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 2 contracts
Samples: Services Agreement, Services Agreement
Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one seven (217) days after first observance of the conditions. Site conditions which an experienced and prudent contractor could have anticipated by visiting the site, familiarizing himself with the local conditions under which the Work is to be performed and correlating his observations with the requirements of the Contract Documents shall not be considered as claims for concealed or unknown conditions, nor shall the locations of utilities which differ from locations provided by the utility companies. The Engineer or Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's ’s cost of, or the required time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Engineer or Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Engineer or Architect shall so notify the Owner NURA and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) days after the Engineer or Architect has given notice of the decision. If the Owner NURA and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Engineer or Architect for initial determination, subject to further proceedings proceeding pursuant to Paragraph 4.4these Contract Documents.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 1 contract
Samples: Trade Contractor Agreement
Claims for Concealed or Unknown Conditions. If conditions are encountered at the Project site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then written notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 7 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or and time required for, performance of for any part of the Project Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or bothSum. If the Architect determines that the conditions at the Project site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner Owner, Program Manager and Contractor in writing, stating the reasons. Claims Written objection by either party in opposition to such determination must be made within twenty-one (21) 7 days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract TimeSum, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.45.5.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 1 contract
Samples: Guaranteed Maximum Price Construction Agreement (Gaylord Entertainment Co /De)
Claims for Concealed or Unknown Conditions. Concealed or unknown physical conditions include utility lines, other man-made structures, storage facilities, Pollutants and Pollutant Facilities, and the like, but do not include conditions arising from Contractor operations, or failure of Contractor to properly protect and safeguard subsurface facilities. Concealed conditions also include naturally-occurring soil conditions outside the range of soil conditions identified through geotechnical investigations, but do not include conditions arising from groundwater, rain, or flood.
4.3.5.1 If conditions are encountered at the site which are (1) subsurface Underground Facilities or otherwise concealed physical or unknown conditions which differ materially from from:
4.3.5.1.1 those indicated in by the Contract Documents Contract; or
4.3.5.1.2 conditions which Contractor could have discovered through site inspection, geotechnical testing, or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found otherwise; then Contractor will give written notice to exist and generally recognized as inherent in construction activities City Engineer no later than five days after Xxxxxxxxxx's first observation of the character provided for in the Contract Documents, then condition and before condition is disturbed. Contractor's failure to provide notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) days after first observance constitutes a waiver of the conditions. The Architect a Claim.
4.3.5.2 City Engineer will promptly investigate such conditions and, if they differ materially and cause an increase concealed or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or bothunknown conditions. If the Architect City Engineer determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract Price or Contract Time is justified, the Architect shall so City Engineer will notify the Owner and Contractor in writing, stating the reasons. Claims If City Engineer determines the conditions differ materially and cause increase or decrease in Contractor’s cost or time required for performance of part of the Work, City Engineer will recommend an adjustment in Contract Price or Contract Time, or both, as provided in Article 7. Opposition by either party in opposition a Party to such the City Engineer’s determination must be made within twenty-one (21) 21 days after the Architect City Engineer has given notice of the decision. If the Owner and Contractor Parties cannot agree on an adjustment in the to Contract Sum Price or Contract Time, the adjustment shall be referred to the Architect for initial determination, is subject to further proceedings pursuant to Paragraph Section 4.4.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 1 contract
Samples: Job Order Contracting Agreement
Claims for Concealed or Unknown Conditions. If conditions are encountered a Concealed Condition is discovered at the site [which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents Documents, or (2) unknown physical conditions of an unusual nature, nature which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents], then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one (21) 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, and if Contractor neither knew nor should have known of such Concealed Condition prior to entering into this Agreement or prior to establishing the Guaranteed Maximum Price, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents or that Contractor either knew or should have known of such Concealed Condition prior to the time established above, and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.
4.3.5.1 No adjustment in the Contract Time or Contract Sum shall be permitted, however, in connection with a concealed or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Project.
Appears in 1 contract
Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or in the Geo-technical report or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally 60 recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than twenty-one 21 three (213) days after first observance of the conditions, and in any case, prior to altering or removing the differing condition. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the 65 Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within twenty-one (21) 21 days after the Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred 70 to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4.
4.3.5.1 No adjustment in . This Agreement is based closely upon the American Institute of Architects 1997 Edition of AIA Document A201, “General Conditions of the Contract Time for Construction”. AIA has not granted specific authorization for this use, nor has Maricopa Community Colleges requested such use. MCCCD pays an annual license fee for unlimited use of all AIA documents. Our use is intended to be an edited version of the AIA standard documents and not intended to override or Contract Sum shall be permitted, however, in connection with a concealed avoid copyright or unknown condition which does not differ materially from those conditions disclosed or which reasonably should have been disclosed by the Contractor's (1) prior inspections, tests, reviews and preconstruction services for the Project, or (2) inspections, test, reviews, and preconstruction services which the Contractor had the opportunity to make or should have performed in connection with the Projectother use of their documents.
Appears in 1 contract
Samples: General Conditions of the Contract for Construction