Completion and Liquidated Damages Sample Clauses

Completion and Liquidated Damages. The Contractor agrees to commence work on the date to be specified in a written "Notice to Proceed" and fully complete the project within the agreed upon consecutive calendar days thereafter. Contractor agrees to pay as liquidated damages, the sum of $50 for each consecutive calendar day thereafter as provided by this bid package and Contract until the project is completed in full. The Bidder will be expected to complete Building Demolition and Site Clearance Services for all properties identified herein within 90 days from the date to commence work as specified in a written "Notice to Proceed", or within a time frame that is agreed to by City and Contractor.
AutoNDA by SimpleDocs
Completion and Liquidated Damages. 1 Completion of Project QICT shall achieve completion as per the Implementation Schedule (Schedule I).
Completion and Liquidated Damages. (IF APPLICABLE) It is understood and agreed that time is of the essence. The Contractor will efficiently, diligently, and expeditiously conduct the work in a manner that will satisfy compliance with approved project schedules and completion by the completion date appearing in the body of this bid.
Completion and Liquidated Damages. The timely completion of the Project is essential to the School District. The School District will incur serious and substantial damages if Substantial Completion of the Work does not occur within the Contract Time. The Contractor is responsible for actual damages for delay unless an amount is inserted on the cover page for liquidated damages, in which case the liquidated damage amount shall apply. Liquidated damages shall not be affected by partial completion, occupancy, or beneficial occupancy.
Completion and Liquidated Damages. A. The commencement and completion dates are essential conditions of this Agreement. The work must begin as stated in the Notice to Proceed. The Contractor must proceed with the work at a rate of progress to ensure full completion within the contract time. The Contractor and the Homeowner expressly agree that the contract time for completing the work is a reasonable time as determined by the parties considering the average climactic and economic conditions and other factors prevailing in the locale. Because time is of the essence in this contract liquidated damages apply to its performance. For each working day that any work remains uncompleted after the final completion time as stated in the notice to proceed, the City may deduct the amount stated below from money due the Contractor:
Completion and Liquidated Damages. Contractor promises that all Work shall be substantially complete on or before the date set forth in each GMP Amendment, if any are executed. Contractor agrees to pay, as liquidated damages to Owner for any delay, the sum of Two Thousand Dollars ($2,000) per day for each day of delay beyond the Substantial Completion date set forth in the applicable GMP Amendment. Owner also has the right to be compensated for other damages that are a direct result of Contractor’s failure to complete the Work as promised. Contractor further promises that all Work shall be finally complete within 60 days after Substantial Completion. Final payment will not be made until the Work is accepted by Owner.

Related to Completion and Liquidated Damages

  • CONTRACT TIME AND LIQUIDATED DAMAGES (7-1-95) (Rev. 12-18-07) 108 SP1 G10 A The date of availability for this contract is September 26, 2016. The completion date for this contract is October 31, 2017. Except where otherwise provided by the contract, observation periods required by the contract will not be a part of the work to be completed by the completion date and/or intermediate contract times stated in the contract. The acceptable completion of the observation periods that extend beyond the final completion date shall be a part of the work covered by the performance and payment bonds. The liquidated damages for this contract are Two Thousand Dollars ($ 2,000.00) per calendar day.

  • Payment of Liquidated Damages If you supply all or some of your milk to a third party during a Month you must, if required by DFMC, immediately pay to DFMC liquidated damages for that Month calculated as follows: $X = W cents x (Y – Z) Where: $X is the amount payable by you to DFMC for the relevant Month. If $X is a negative amount, no amount is payable by you. Y is the average monthly litres you have supplied to DFMC based on the 12 months immediately preceding the relevant Month (or in the event you have not supplied DFMC for 12 months, the average monthly litres you have supplied to DFMC during the period you have supplied DFMC). Z is the number of litres supplied to DFMC by you for the relevant Month.

  • Breach of Contract and Liquidated Damages A. Where OGS determines that the Contractor is not in compliance with the requirements of this Contract, and the Contractor refuses to comply with such requirements, or if it is found to have willfully and intentionally failed to comply with the MWBE participation goals set forth in the Contract, the Contractor shall be obligated to pay liquidated damages to OGS.

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.

  • Notice of Liquidated Damages System Agency will formally notify Grantee in writing when liquidated damages action is imposed, stating the nature of the action, the reasons for imposing, and the method of appealing. Grantee must submit a written appeal, within ten (10) calendar days of receipt of the notice, to the SUD email box, XxxxxxxxxXxxxx.Xxxxxxxxx@xxxx.xxxxx.xx.xx.

  • Withholding for unpaid wages and liquidated damages The FHWA or the contacting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2.) of this section.

  • Liquidated Damages The Company’s obligations to pay any partial liquidated damages or other amounts owing under the Transaction Documents is a continuing obligation of the Company and shall not terminate until all unpaid partial liquidated damages and other amounts have been paid notwithstanding the fact that the instrument or security pursuant to which such partial liquidated damages or other amounts are due and payable shall have been canceled.

  • Violation; liability for unpaid wages; liquidated damages In the event of any violation of the clause set forth in paragraph (1.) of this section, the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (1.) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (1.) of this section.

  • Liquidated Damages Security The Board may require that a Member that has two (2) or more NMFS fishing regulation violations, or which has breached this Agreement or another sector’s operations plan on two (2) or more occasions, post a bond or obtain a letter of credit securing such Member’s payment and performance obligations under this Agreement in such amounts as the Board deems appropriate, or may require such Member to personally guaranty, and/or have other Members or third parties personally guaranty, such Member’s payment and performance obligations under this Agreement.

  • Deduction of Damages from Contract Price Upon prior written notice being issued to the Contractor, CMHA may deduct all or any part of the damages resulting from Contractor’s default from any part of the price still due on this Agreement.

Time is Money Join Law Insider Premium to draft better contracts faster.