Claims of Force Majeure. In addition to the conditions set forth in Section 8.1(a) above and in the definition of Force Majeure Event, a Party may rely on a claim of a Force Majeure Event for purposes of this Agreement only to the extent that such Party: (i) provides prompt notice of such Force Majeure Event to the other Party giving an estimate of its expected duration and the probable impact on the performance of its obligations under this Agreement and, if applicable, the construction and operation of the Project; (ii) provides weekly updates during the continuance of the Force Majeure Event that (A) summarize the measures taken by the affected Party and that the affected Party plans to take in order to mitigate the impact of such Force Majeure Event and (B) provide an estimate of the expected duration of the period during which the performance by the affected Party of its material obligations under this Agreement will be prevented or the construction or operation of the Project, as applicable, will be adversely affected due to the Force Majeure Event; (iii) exercises all commercially reasonable efforts to continue to perform its obligations under this Agreement and to mitigate or limit damages to the other Party; and (iv) expeditiously, and at its sole cost and expense, takes all commercially reasonable actions necessary to correct or cure the Force Majeure Event or impact thereof so that any suspension of performance or adverse impact on the construction or operation of the Project, as applicable, is no greater in scope and no longer in duration than is necessary based on the Force Majeure Event.
Appears in 5 contracts
Samples: Storage Capacity Agreement, Storage Capacity Agreement, Storage Capacity Agreement
Claims of Force Majeure. In addition To the extent either Party intends to the conditions set forth in Section 8.1(a) above and in the definition of Force Majeure Event, a Party may rely on a claim of a Force Majeure Event for purposes of this Agreement only to Agreement, such Party (the extent that such “Claiming Party”) shall:
(i) provides prompt provide notice and details of such the Force Majeure Event to the other Party giving as soon as practicable, but in no event later than five (5) Business Days. The notice shall include an estimate of its expected duration and the probable impact on the performance of its obligations under this Agreement and, if applicable, the construction and operation of the ProjectAgreement;
(ii) provides provide weekly updates during the continuance of the Force Majeure Event that
that (A) summarize the measures taken by the affected Claiming Party and that the affected Claiming Party plans to take in order to mitigate the impact of such Force Majeure Event and (B) provide an estimate of the expected duration of the period during which the performance by the affected Claiming Party of its material obligations under this Agreement will be prevented or the construction or operation of the Project, as applicable, will be adversely affected due to the Force Majeure Event;
(iii) exercises all commercially reasonable efforts to continue to perform its obligations under this Agreement and to mitigate or limit damages to the other Party; and
(iv) expeditiously, and at its sole cost and expense, takes all commercially reasonable actions necessary to correct or cure the Force Majeure Event or impact thereof so that any suspension of performance or adverse impact on the construction or operation of the Project, as applicable, is no greater in scope and no longer in duration than is necessary based on the Force Majeure Event.
Appears in 4 contracts
Samples: Wholesale Renewable Power and Storage Capacity Purchase Agreement, Wholesale Renewable Power and Storage Capacity Purchase Agreement, Wholesale Renewable Power Purchase Agreement
Claims of Force Majeure. In addition to the conditions set forth in Section 8.1(a10.1(a) above and in the definition of Force Majeure Event, a Party may rely on a claim of a Force Majeure Event for purposes of this Agreement only to the extent that such Party:
(i) provides prompt notice of such Force Majeure Event to the other Party giving an estimate of its expected duration and the probable impact on the performance of its obligations under this Agreement and, if applicable, the construction and operation of the Project;
(ii) provides weekly updates during the continuance of the Force Majeure Event that
that (A) summarize the measures taken by the affected Party and that the affected Party plans to take in order to mitigate the impact of such Force Majeure Event and (B) provide an estimate of the expected duration of the period during which the performance by the affected Party of its material obligations under this Agreement will be prevented or the construction or operation of the Project, as applicable, will be adversely affected due to the Force Majeure Event;
(iii) exercises all commercially reasonable efforts to continue to perform its obligations under this Agreement and to mitigate or limit damages to the other Party; and
(iv) expeditiously, and at its sole cost and expense, takes all commercially reasonable actions necessary to correct or cure the Force Majeure Event or impact thereof so that any suspension of performance or adverse impact on the construction or operation of the Project, as applicable, is no greater in scope and no longer in duration than is necessary based on the Force Majeure Event.
Appears in 2 contracts
Samples: Storage Capacity Agreement, Storage Capacity Agreement
Claims of Force Majeure. In addition to the conditions set forth in Section 8.1(a) above and in the definition of Force Majeure Event, a Party may rely on a claim of a Force Majeure Event for purposes of this Agreement only to the extent that such Party:
(i) provides prompt notice of such Force Majeure Event to the other Party giving an estimate of its expected duration and the probable impact on the performance of its obligations under this Agreement and, if applicable, the construction and operation of the Project;
(ii) provides weekly updates during the continuance of the Force Majeure Event that
that (A) summarize the measures taken by the affected Party and that the affected Party plans to take in order to mitigate the impact of such Force Majeure Event and (B) provide an estimate of the expected duration of the period during which the performance by the affected Party of its material obligations under this Agreement will be prevented or the construction or operation of the Project, as applicable, will be adversely affected due to the Force Majeure Event;
(iii) exercises all commercially reasonable efforts to continue to perform its obligations under this Agreement and to mitigate or limit damages to the other Party; and
(iv) expeditiously, and at its sole cost and expense, takes all commercially reasonable actions necessary to correct or cure the Force Majeure Event or impact thereof so that any suspension of performance or adverse impact on the construction or operation of the Project, as applicable, is no greater in scope and no longer in duration than is necessary based on the Force Majeure Event.
Appears in 2 contracts
Samples: Storage Capacity Agreement, Storage Capacity Agreement