Common use of Commercial Operation Deadline Clause in Contracts

Commercial Operation Deadline. Subject to extensions made pursuant to Sections 1.04(a), 3.06(c) or 5.03, the Commercial Operation Date must be no later than one hundred twenty (120) days from the Initial Synchronization Date (“Commercial Operation Deadline”).

Appears in 3 contracts

Samples: Renewable Power Purchase and Sale Agreement (Montauk Renewables, Inc.), Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement

AutoNDA by SimpleDocs

Commercial Operation Deadline. Subject to extensions made pursuant to Sections 1.04(a), 1.04(b), 3.06(c) or 5.03, the Commercial Operation Date must be no later than one hundred twenty (120) days from the Initial Synchronization Date (“Commercial Operation Deadline”).

Appears in 2 contracts

Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement

AutoNDA by SimpleDocs

Commercial Operation Deadline. Subject to extensions made pursuant to Sections 1.04(a), 1.04(b), 3.06(c) or 5.03, the Commercial Operation Date must be no later than one hundred twenty (120) days from the Initial Synchronization Date (“Commercial Operation Deadline”).

Appears in 1 contract

Samples: Renewable Power Purchase and Sale Agreement