COMPENSABLE DELAY. A Delay for which Contractor may be entitled under the Contract Documents to both an extension of the Contract Time and an adjustment of the Contract Sum for additional compensation.
Appears in 29 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
COMPENSABLE DELAY. A Delay for which Contractor may be entitled under the Contract Documents to both an extension of the Contract Time and an adjustment of the Contract Sum for additional compensation.. "Compensable Delay" means any Delay to the path of activities that is critical to Contractor’s Substantial Completion of the Work within the Contract Time, which Delay is all of the following: