Changes in Contract Time. All Change Orders must state that the Contract Time and the Material Completion and Occupancy Date either are not changed or are increased or decreased by a specific number of Days. The CONTRACTOR must provide written justification for the extension to the Design Professional and to the Owner. The written justification must demonstrate an anticipated actual increase in the time required to complete the Work beyond that allowed by the Contract as adjusted by prior Change Orders to the Contract. No extension to the Contract Time shall be allowed unless the additional or changed Work increases the length of the critical path beyond the Material Completion and Occupancy Date. If approved, the increase in time required to complete the Work shall be added to the Contract Time. The Owner may decrease, by Change Order, the Contract Time when an Owner-requested deletion from the Work results in a decrease in the actual time required to complete the Work as demonstrable on the critical path of the Construction Progress Schedule. Eligibility and processing requirements for Time Dependent Overhead Costs for compensable delay is addressed in Article 3.3.8 and 3.3.10.
Changes in Contract Time. All Change Orders must state that the Contract Time and the Material Completion and Occupancy Date either are not changed or are increased or decreased by a specific number of Days. The Contractor must provide written justification for the extension to the Design Professional and to the Owner. The written justification must demonstrate an anticipated actual increase in the time required to complete the Work beyond that allowed by the Contract as adjusted by prior Change Orders to the Contract. No extension to the Contract Time shall be allowed unless the additional or changed Work increases the length of the critical path beyond the Material Completion and Occupancy Date. If approved, the increase in time required to complete the Work shall be added to the Contract Time. The Owner may decrease, by Change Order, the Contract Time when an Owner-requested deletion from the Work results in a decrease in the actual time required to complete the Work as demonstrable on the CPM Schedule.
Changes in Contract Time. The critical path schedule as the term is used herein shall be based on the current version of Contractor’s schedule for the project and accepted by County just prior to the commencement of the modification, asserted delay, suspension or interruption. Contractor may request a Change Order for an extension of time, which shall be accompanied by a critical path impact analysis reflecting the added or changed work including an analysis of the impact on unchanged activities.
Changes in Contract Time. All Change Orders must state that the Contract Time and the Material Completion Date either are not changed or are increased or decreased by a specific number of Days. The CM/GC must provide written justification for the extension to the Design Professional and to the Owner. The written justification must demonstrate an anticipated actual increase in the time required to complete the Work beyond that allowed by the Contract as adjusted by prior Change Orders to the Contract. No extension to the Contract Time shall be allowed unless the additional or changed Work increases the length of the critical path beyond the Material Completion Date. If approved, the increase in time required to complete the Work shall be added to the Contract Time. The Owner may decrease, by Change Order, the Contract Time when an Owner-requested deletion from the Work results in a decrease in the actual time required to complete the Work as demonstrable on the critical path of the Construction Progress Schedule.
Changes in Contract Time. All Change Orders must, state either that the Contract Time and the Material Completion Date are not changed, or are increased, or decreased by a specific number of Days. The CMR must provide a time impact study utilizing the current progress schedule and provide written justification for the extension to the Design Profession and the Board. The written justification must demonstrate an anticipated actual increase in the time required to complete the Work beyond that allowed by the Contract as adjusted by prior Change Orders to the Contract. No extension to the Contract Time shall be allowed unless the additional or changed Work increases the length of the critical path beyond the Material Completion Date. If approved, the increase in time required to complete the Work shall be added to the Contract Time. The Board may decrease, by Change Order, the Contract Time when an Board-requested deletion from the Work results in a decrease in the actual time required to complete the Work as demonstrable on the critical path of the Construction Progress Schedule.
Changes in Contract Time. 11.2.1. An extension in Contract Time will be justified only to the extent that the Contractor demonstrates, with comprehensive and detailed documentation, that the Delay is not reasonably anticipatable under the circumstances, is not caused by act or omission within the control of the Contractor, and, furthermore, that the Delay necessarily extends the Work, or portion of the Work in question, beyond the pertinent Contract Time. If the Owner determines that the Contractor’s documentation is insufficient to allow a thorough evaluation of the time extension request, the Contractor shall further support the request through a detailed analysis of the Progress Schedule Revision Submittal.
11.2.2. Examples of events that may justify an extension in Contract Time include acts of God or the public enemy; acts of the U.S. Government, the State or a Political Subdivision, each acting in its public capacity (including acts as permitting agency); acts of a Public Utility acting in its public capacity; fires, floods, epidemics, quarantine restrictions; strikes, freight embargoes; unusual weather (unusual in the sense of frequency or severity vis-à-vis the prior five
Changes in Contract Time. 16.1 The contract price may be changed only by a change order. The value of any work covered by a change order or any claim for increase or decrease in the contract price shall be determined by one or more of the following methods in the order of precedence listed below:
16.1.1 Unit prices previously approved.
16.1.2 An agreed lump sum.
16.1.3 The actual cost of:
a) Labor, including xxxxxxx;
b) Materials entering permanently into the work;
c) The ownership or rental cost of construction plant and equipment during the time of use on the extra work;
d) Power and consumable supplies for the operation of power equipment;
Changes in Contract Time. A PCO shall also include any changes in time required to complete the Project. Any additional time requested shall not be the number of days to make the proposed change, but must be based upon the impact to the Construction Schedule as defined in the Contract Documents. If Designer/Builder fails to request a time extension in a PCO, then the Designer/Builder is thereafter precluded from requesting time and/or claiming a delay.
Changes in Contract Time. Adjustment in the Agreement time will be made by modification pursuant to the provisions of Article 3
Changes in Contract Time. Only Construction change Order shall grant changes in Contract Time. Claims for disputes concerning Contract Time shall be determined in accordance with Article 13 of this Agreement.