Completion of Outstanding Work and Remedying Defects. In order that the Works and Contractor's Documents, and each Section shall be in the condition required by the Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as soon as practicable thereafter, the Contractor shall: (a) complete any work which is outstanding on the date stated in a Taking-Over Certificate, within such reasonable time as is instructed by the Engineer, and (b) execute all work required to remedy defects or damage, as may be notified by (or on behalf of) the Employer on or before the expiry date of the Defects Notification Period for the Works or Section (as the case may be). If a defect appears or damage occurs, the Contractor shall be notified accordingly, by (or on behalf) the Employer.
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Completion of Outstanding Work and Remedying Defects. In order that the Works and Contractor's ’s Documents, and each Section Section, shall be in the condition required by the Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as soon as practicable thereafter, the Contractor shall:
(a) complete any work which is outstanding on the date stated in a Taking-Over Certificate, within such reasonable time as is instructed by the Engineer, and
(b) execute all work required to remedy defects or damage, as may be notified by (or on behalf of) the Employer on or before the expiry date of the Defects Notification Period for the Works or Section (as the case may be). If a defect appears or damage occurs, the Contractor shall be notified accordingly, by (or on behalfbehalf of) the Employer.
Appears in 2 contracts
Samples: Unit Price Contract, Unit Price Contract
Completion of Outstanding Work and Remedying Defects. In order that the Works and Contractor's Documents, and each Section Section, shall be in the condition required by the Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as soon as practicable thereafter, the Contractor shall:
(a) complete any work which is outstanding on the date stated in a Taking-Over Certificate, within such reasonable time as is instructed by the Engineer, and
(b) execute all work required to remedy defects or damage, as may be notified by (or on behalf of) the Employer on or before the expiry date of the Defects Notification Period for the Works or Section (as the case may be). SAMPLE If a defect appears or damage occurs, the Contractor shall be notified accordingly, by (or on behalfbehalf of) the Employer.
Appears in 1 contract
Samples: Contract Agreement