Completion Tests. 14.1.1 At least 30 (thirty) days prior to the likely completion of the Hospital or any part thereof (Phase-I and/or Phase-II and/or any Additional Capacity developed by the Concessionaire in its own discretion, as the case may be), the Concessionaire shall notify the Independent Engineer and the Monitoring Agency of its intent to subject the Hospital or any part thereof to Completion Tests. The date and time of each Test shall be determined by the Independent Engineer and the Monitoring Agency in consultation with the Concessionaire, and notified to the Authority who may designate its representative to witness the Completion Tests. For the avoidance of any doubt, the Independent Engineer and the Monitoring Agency may separately conduct the relevant Completion Tests. The Concessionaire shall provide such assistance as the Independent Engineer and the Monitoring Agency may reasonably require for conducting the Completion Tests. In the event that of the Concessionaire, the Independent Engineer and the Monitoring Agency failing to mutually agree on the dates for conducting the Completion Tests, the Concessionaire shall fix the dates by not less than 7 (seven) days' notice to the Independent Engineer and the Monitoring Agency. 14.1.2 All Completion Tests shall be conducted in accordance with Schedule 12. The Independent Engineer and the Monitoring Agency shall observe, monitor and review the results of the Completion Tests to determine compliance of the Hospital with Specifications and Standards and if it is reasonably anticipated or determined by the Independent Engineer or the Monitoring Agency, as the case may be, during the course of any Completion Test that the Hospital or any part thereof does not meet the Specifications and Standards, it shall have the right to suspend or delay such Completion Test and require the Concessionaire to remedy and rectify the defects or deficiencies. Upon completion of each Completion Test, the Independent Engineer and the Monitoring Agency shall provide to the Concessionaire and the Authority copies of all Completion Test data including detailed Completion Test results. For the avoidance of doubt, it is expressly agreed that the Independent Engineer and/or the Monitoring Agency may require the Concessionaire to carry out or cause to be carried out additional Completion Tests, in accordance with Good Industry Practice, for determining the compliance of the Hospital with Specifications and Standards.
Appears in 6 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Completion Tests. 14.1.1 At least 30 (thirty) days prior to the likely completion of the Hospital or any part thereof (Phase-I and/or Phase-II and/or any Additional Capacity developed by Construction Works for the Concessionaire in its own discretion, as the case may be)Phase I, the Concessionaire shall notify the Independent Engineer and or the Monitoring Agency Independent Panel, as the case may be, of its intent to subject the Hospital Project or any part thereof to Completion Tests. The date and time of each Completion Test shall be determined by the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, in consultation with the Concessionaire, and notified to the Authority who may designate its representative to witness the Completion Tests. For the avoidance of any doubt, the Independent Engineer and the Monitoring Agency may separately conduct the relevant Completion Tests. The Concessionaire shall provide such assistance as the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, may reasonably require for conducting the Completion Tests. In the event that of the Concessionaire, the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, failing to mutually agree on the dates for conducting the Completion Tests, the Concessionaire shall fix the dates by not less than 7 (seven) days' notice to the Independent Engineer and the Monitoring AgencyIndependent Panel, as the case may be.
14.1.2 All Completion Tests shall be conducted in accordance with Schedule 12. I. The Independent Engineer and Independent Panel, as the Monitoring Agency case may be, shall observe, monitor and review the results of the Completion Tests to determine compliance of the Hospital Project, as the case may be, with Specifications and Standards and if it is reasonably anticipated or determined by the Independent Engineer or the Monitoring AgencyIndependent Panel, as the case may be, during the course of any Completion Test that the Hospital Phase I or any part thereof thereof, does not meet the Specifications and Standards, it shall have the right to suspend or delay such Completion Test and require the Concessionaire to remedy and rectify the defects or deficiencies. Upon completion of each Completion Test, the Independent Engineer and and/or the Monitoring Agency Independent Panel, as the case may be, shall provide to the Concessionaire and the Authority copies of all Completion Test data including detailed Completion Test results. For the avoidance of doubt, it is expressly agreed that the Independent Engineer and/or the Monitoring Agency may require the Concessionaire to carry out or cause to be carried out additional Completion Tests, in accordance with Good Industry Practice, for determining the compliance of the Hospital Project, as the case may, with Specifications and Standards.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Completion Tests. 14.1.1 At least 30 (thirty) days prior to the likely completion of the Hospital Construction Works for Project or any part thereof (Phase-0 and/or Phase-I and/or Phase-II and/or any Additional Capacity developed by the Concessionaire in its own discretionOptional Development), as the case may be), the Concessionaire shall notify the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, of its intent to subject the Hospital Project or any part thereof to Completion Tests. The date and time of each Test shall be determined by the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, in consultation with the Concessionaire, and notified to the Authority who may designate its representative to witness the Completion Tests. For the avoidance of any doubt, the Independent Engineer and the Monitoring Agency may separately conduct the relevant Completion Tests. The Concessionaire shall provide such assistance as the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, may reasonably require for conducting the Completion Tests. In the event that of the Concessionaire, the Independent Engineer and the Monitoring Agency Independent Panel, as the case may be, failing to mutually agree on the dates for conducting the Completion Tests, the Concessionaire shall fix the dates by not less than 7 (seven) days' notice to the Independent Engineer and the Monitoring AgencyIndependent Panel, as the case may be.
14.1.2 All Completion Tests shall be conducted in accordance with Schedule 12. J. The Independent Engineer and Independent Panel, as the Monitoring Agency case may be, shall observe, monitor and review the results of the Completion Tests to determine compliance of the Hospital Project, as the case may be, with Specifications and Standards and if it is reasonably anticipated or determined by the Independent Engineer or the Monitoring AgencyEngineer, as the case may be, during the course of any Completion Test that the Hospital Project, as the case may, be or any part thereof does not meet the Specifications and Standards, it shall have the right to suspend or delay such Completion Test and require the Concessionaire to remedy and rectify the defects or deficiencies. Upon completion of each Completion Test, the Independent Engineer and and/or the Monitoring Agency Independent Panel, as the case may be, shall provide to the Concessionaire and the Authority copies of all Completion Test data including detailed Completion Test results. For the avoidance of doubt, it is expressly agreed that the Independent Engineer and/or the Monitoring Agency may require the Concessionaire to carry out or cause to be carried out additional Completion Tests, in accordance with Good Industry Practice, for determining the compliance of the Hospital Project, as the case may, with Specifications and Standards.
Appears in 1 contract
Samples: Concession Agreement
Completion Tests. 14.1.1 At least 30 thirty (thirty30) days prior to the likely completion of the Hospital or any part thereof (Phase-I and/or Phase-II and/or any Additional Capacity developed by the Concessionaire in its own discretion, as the case may be)expected Project Highway Section Completion Date and Commercial Operations Date respectively, the Concessionaire shall notify issue a notice to the Authority and the Independent Engineer (the Completion Tests Date Notice) fixing a date and time for performance of the Completion Tests (the Proposed Completion Tests Date).
14.1.2 The Proposed Completion Tests Date proposed by the Concessionaire shall be final for the conducting of the Completion Tests; provided, however, in the event the Proposed Completion Tests Date is unacceptable to the Independent Engineer and/or the Authority, the Concessionaire, the Authority and the Independent Engineer shall meet within seven (7) days of the Authority and Independent Engineer’s receipt of the Concessionaire’s Completion Tests Date Notice with an aim to mutually agree on an alternative date and time for performance of the Completion Tests, which date shall be no later than ten (10) days from the Proposed Completion Tests Date. If the Parties are unable to mutually agree on an alternative date and time for performance of the Completion Tests, the Concessionaire shall be entitled (with prior Notification to the Independent Engineer and the Monitoring Agency Authority) to carry out the Completion Tests on or after the tenth (10th) day from the Proposed Completion Tests Date.
14.1.3 Subject to the terms of its intent this Agreement, in the event any Completion Tests are to subject be repeated due to reasons not attributable to the Hospital or any part thereof to Completion Tests. The date and time of each Test shall be Authority, as determined by the Independent Engineer Engineer, such Completion Tests shall be repeated on account of the Concessionaire.
14.1.4 The Completion Tests shall be attended by the Authority Representative and such other representatives of the Authority as the Authority may nominate in writing, subject to notification of the same to the Concessionaire and the Monitoring Agency in consultation with the Concessionaire, and notified to the Authority who may designate its representative to witness the Completion Tests. For the avoidance of any doubt, the Independent Engineer and the Monitoring Agency may separately conduct the relevant Completion Tests. Engineer.
14.1.5 The Concessionaire shall provide such assistance as the Independent Engineer and the Monitoring Agency may reasonably require for conducting the Completion Tests. In the event that of the Concessionaire, the Independent Engineer and the Monitoring Agency failing to mutually agree on the dates for conducting the Completion Tests, the Concessionaire shall fix the dates by not less than 7 (seven) days' notice to the Independent Engineer and the Monitoring Agency.
14.1.2 All Completion Tests shall be conducted in accordance with Schedule 12. The Independent Engineer and the Monitoring Agency shall observe, monitor and review the results of the Completion Tests to determine compliance of the Hospital with Specifications and Standards and if it is reasonably anticipated or determined by the Independent Engineer or the Monitoring Agency, as the case may be, during the course of any Completion Test that the Hospital or any part thereof does not meet the Specifications and Standards, it shall have the right to suspend or delay such Completion Test and require the Concessionaire to remedy and rectify the defects or deficiencies. Upon completion of each Completion Test, the Independent Engineer and the Monitoring Agency shall provide to the Concessionaire and the Authority copies of all Completion Test data including detailed Completion Test results. For the avoidance of doubt, it is expressly agreed that the Independent Engineer and/or the Monitoring Agency may require the Concessionaire to carry out or cause to be carried out additional Completion Tests, in accordance with Good Industry Practice, for determining the compliance of the Hospital with Specifications and Standards.
Appears in 1 contract
Samples: Concession Agreement