Common use of Computation of Time / Adverse Weather Clause in Contracts

Computation of Time / Adverse Weather. 15.2.1 Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein and only if all of the following conditions are met: 15.2.1.1 The weather conditions constitute Adverse Weather, as defined herein; 15.2.1.2 Developer can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather;

Appears in 2 contracts

Samples: Facilities Lease, Facilities Lease

AutoNDA by SimpleDocs

Computation of Time / Adverse Weather. 15.2.1 Developer 14.2.1. The Contractor will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein Contractor and only if all of the following conditions are met: 15.2.1.1 14.2.1.1. The weather conditions constitute Adverse Weather, as defined herein;; 14. 15.2.1.2 Developer 2.1.2. Contractor can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather;

Appears in 1 contract

Samples: Site Lease

Computation of Time / Adverse Weather. 15.2.1 Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein and only if all of the following conditions are met: 15.2.1.1 The weather conditions constitute Adverse Weather, as defined herein; 15.2.1.2 Developer can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather;

Appears in 1 contract

Samples: Facilities Lease

Computation of Time / Adverse Weather. 15.2.1 1The Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein required in Articles 16 and 17, and only if all of the following conditions are met: 15.2.1.1 The weather conditions constitute Adverse Weather, as defined herein; 15.2.1.2 Developer can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather;

Appears in 1 contract

Samples: General Construction Agreement

AutoNDA by SimpleDocs

Computation of Time / Adverse Weather. 15.2.1 Developer will only be allowed a time extension for Adverse Weather conditions if requested by Developer in compliance with the time extension request procedures herein and only if all of the following conditions are met: 15.2.1.1 The weather conditions constitute Adverse Weather, as defined herein; 15.2.1.2 Developer can verify that the Adverse Weather caused delays in excess of five (5) hours of the indicated labor required to complete the scheduled tasks of Work on the day affected by the Adverse Weather; 15.2.1.3 Developer’s crew is dismissed as a result of the Adverse Weather;Adverse

Appears in 1 contract

Samples: Facilities Lease