Conditions Applicable to Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Project Architect has determined that the Work or designated portion thereof is sufficiently complete and in working order in accordance with the Contract Documents, including but not limited to the following: 1. All project systems included in the Work or designated portion thereof have been successfully tested and are fully operational, and factory startup of equipment has been completed. 2. All required governmental inspections and certifications required of the Work have been made, approved, posted, and copies are on file with the Owner with AIA forms if required. 3. Designated initial training instruction of Owner’s personnel in the operation of the project systems has been completed. 4. All the required finishes set out in the Construction Documents are in place. 5. The only remaining Work shall be minor in nature so that Owner can occupy the work or the applicable portion of the Work for all of its intended purposes on that date. 6. Completion of the Work by Contractor will not materially interfere with or hamper Owner’s normal school operations or other intended use. Contractor must coordinate with school schedules. 7. As further condition of a determination of Substantial Completion, Contractor shall certify that all remaining Work shall be complete within thirty (30) days or Contractor shall provide a schedule for Final Completion approved in writing by Owner. In the event final completion is not achieved, liquidated damages may be reinstated. 8. Technology cabling shall be in place, tested for connectivity, cable ends terminated and labeled in accordance with the district’s labeling scheme. 9. Fire alarm systems operational, tested, approved, and a graphic map installed. 10. All life safety systems, fire suppression, public address systems, and related items shall be tested and operational. 11. Electronic hardware installation is complete and operational. 12. Paved areas including, but not limited to, parking lots, driveways, curb and gutters, sidewalks, including areas required to be replaced. 13. Certificate of Compliance issued by the city or appropriate authority having jurisdiction for site work. 14. Temporary Certificate of Occupancy or Certificate of Occupancy issued by the city or appropriate authority having jurisdiction with no exceptions or outstanding items. 15. Sanitization of domestic water systems. 16. Verification of floor drains operation, free of obstructions and free-draining. 17. Removal of temporary facilities. 18. Removal of site obstructions, construction debris, and cleanup of site. 19. Submit written request for inspection to Architect and Owner. 20. Warranties will commence on date of Final Completion. 21. Receipt of approved Operations and Maintenance Manuals including product warranties. 22. Training of Staff.
Appears in 3 contracts
Samples: Construction Contract, Construction Agreement, Design Bid Build Contractor Services
Conditions Applicable to Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Project Architect has determined that the Work or designated portion thereof is sufficiently complete and in working order in accordance with the Contract Documents, including but not limited to the following:
1. All project systems included in the Work or designated portion thereof have been successfully tested and are fully operational, and factory startup start up of equipment has been completed.
2. All required governmental inspections and certifications required of the Work have been made, approved, posted, and copies are on file with the Owner with AIA forms if required.
3. Designated initial training instruction of Owner’s personnel in the operation of the project systems has been completed.
4. All the required finishes set out in the Construction Documents are in place.
5. The only remaining Work shall be minor in nature so that Owner can occupy the work or the applicable portion of the Work for all of its intended purposes on that date.
6. Completion of the Work by Contractor will not materially interfere with or hamper Owner’s normal school operations or other intended use. Contractor must coordinate with school schedules.
7. As further condition of a determination of Substantial Completion, Contractor shall certify that all remaining Work shall be complete within thirty (30) days or Contractor shall provide a schedule for Final Completion approved in writing by Owner. In the event final completion is not achieved, liquidated damages may be reinstated.
8. Technology cabling shall be in place, tested for connectivity, cable ends terminated and labeled in accordance with the district’s labeling scheme.
9. Fire alarm systems operational, tested, approved, and a graphic map installed.
10. All life safety systems, fire suppression, public address systems, and related items shall be tested and operational.
11. Electronic hardware installation is complete and operational.
12. Paved areas including, but not limited to, parking lots, driveways, curb and gutters, sidewalks, including areas required to be replaced.
13. Certificate of Compliance issued by the city or appropriate authority having jurisdiction for site work.
14. Temporary Certificate of Occupancy or Certificate of Occupancy issued by the city or appropriate authority having jurisdiction with no exceptions or outstanding items.
15. Sanitization of domestic water systems.
16. Verification of floor drains operation, free of obstructions and free-draining.
17. Removal of temporary facilities.
18. Removal of site obstructions, construction debris, and cleanup of site.
19. Submit written request for inspection to Architect and Owner.
20. Warranties will commence on date of Final Completion.
21. Receipt of approved Operations and Maintenance Manuals including product warranties.
22. Training of Staff.
Appears in 2 contracts
Samples: Construction Agreement, Construction Agreement
Conditions Applicable to Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Project Architect has determined that the Work or designated portion thereof is sufficiently complete and in working order in accordance with the Contract Documents, including but not limited to the following:
1. All project systems included in the Work or designated portion thereof have been successfully tested and are fully operational, and factory startup of equipment has been completed.
2. All required governmental inspections and certifications required of the Work have been made, approved, posted, and copies are on file with the Owner with AIA forms if required.
3. Designated initial training instruction of Owner’s personnel in the operation of the project systems has been completed.
4. All the required finishes set out in the Construction Documents are in place.
5. The only remaining Work shall be minor in nature so that Owner can occupy the work or the applicable portion of the Work for all of its intended purposes on that date.
6. Completion of the Work by Contractor will not materially interfere with or hamper Owner’s normal school operations or other intended use. Contractor must coordinate with school schedules.
7. As further condition of a determination of Substantial Completion, Contractor shall certify that all remaining Work shall be complete within thirty (30) days or Contractor shall provide a schedule for Final Completion approved in writing by Owner. In the event final completion is not achieved, liquidated damages may be reinstated.
8. Technology cabling shall be in place, tested for connectivity, cable ends terminated and labeled in accordance with the district’s labeling scheme.
9. Fire alarm systems operational, tested, approved, and a graphic map installed.
10. All life safety systems, fire suppression, public address systems, and related items shall be tested and operational.
11. Electronic hardware installation is complete and operational.
12. Paved areas including, but not limited to, parking lots, driveways, curb and gutters, sidewalks, including areas required to be replaced.
13. Certificate of Compliance issued by the city or appropriate authority having jurisdiction for site work.
14. Temporary Certificate of Occupancy or Certificate of Occupancy issued by the city or appropriate authority having jurisdiction with no exceptions or outstanding items.
15. Sanitization of domestic water systems.
16. Verification of floor drains operation, free of obstructions and free-drainingfree‐draining.
17. Removal of temporary facilities.
18. Removal of site obstructions, construction debris, and cleanup of site.
19. Submit written request for inspection to Architect and Owner.
20. Warranties will commence on date of Final Completion.
21. Receipt of approved Operations and Maintenance Manuals including product warranties.
22. Training of Staff.
Appears in 2 contracts
Samples: Construction Agreement, Construction Agreement
Conditions Applicable to Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Project Architect has determined that the Work or designated portion thereof is sufficiently complete and in working order in accordance with the Contract Documents, including but not limited to the following:
1. All project systems included in the Work or designated portion thereof have been successfully tested and are fully operational, and factory startup of equipment has been completed.
2. All required governmental inspections and certifications required of the Work have been made, approved, posted, and copies are on file with the Owner with AIA forms if required.
3. Designated initial training instruction of Owner’s personnel in the operation of the project systems has been completed.
4. All the required finishes set out in the Construction Documents are in place.
5. The only remaining Work shall be minor in nature so that Owner can occupy the work or the applicable portion of the Work for all of its intended purposes on that date.
6. Completion of the Work by Contractor will not materially interfere with or hamper Owner’s normal school operations or other intended use. Contractor must coordinate with school schedules.
7. As further condition of a determination of Substantial Completion, Contractor shall certify that all remaining Work shall be complete within thirty (30) days or Contractor shall provide a schedule for Final Completion approved in writing by Owner. In the event final completion is not achieved, liquidated damages may be reinstated.
8. Technology cabling shall be in place, tested for connectivity, cable ends terminated and labeled in accordance with the district’s labeling scheme.
9. Fire alarm systems operational, tested, approved, and a graphic map installed.
10. All life safety systems, fire suppression, public address systems, and related items shall be tested and operational.
11. Electronic hardware installation is complete and operational.
12. Paved areas including, but not limited to, parking lots, driveways, curb and gutters, sidewalks, including areas required to be replaced.
13. Certificate of Compliance issued by the city or appropriate authority having jurisdiction for site work.
14. Temporary Certificate of Occupancy or Certificate of Occupancy issued by the city or appropriate authority having jurisdiction with no exceptions or outstanding items.
15. Sanitization of domestic water systems.
16. Verification of floor drains operation, free of obstructions and free-drainingfree‐draining.
17. Removal of temporary facilities.
18. Removal of site obstructions, construction debris, and cleanup of site.
19. Submit written request for inspection to Architect and Owner.
20. Warranties will commence on date of Final Substantial Completion.
21. Receipt of approved Operations and Maintenance Manuals including product warranties.
22. Training of Staff.
Appears in 1 contract
Samples: Design Bid Build Contractor Services
Conditions Applicable to Substantial Completion. Substantial Completion is the stage in the progress of the Work when the Project Architect has determined that the Work or designated portion thereof is sufficiently complete and in working order in accordance with the Contract Documents, including but not limited to the following:
1. All project systems included in the Work or designated portion thereof have been successfully tested and are fully operational, and factory startup start up of equipment has been completed.
2. All required governmental inspections and certifications required of the Work have been made, approved, posted, and copies are on file with the Owner with AIA forms if required.
3. Designated initial training instruction of Owner’s personnel in the operation of the project systems has been completed.
4. All the required finishes set out in the Construction Documents are in place.
5. The only remaining Work shall be minor in nature so that Owner can occupy the work or the applicable portion of the Work for all of its intended purposes on that date.
6. Completion of the Work by Contractor will not materially interfere with or hamper Owner’s normal school operations or other intended use. Contractor must coordinate with school schedules.
7. As further condition of a determination of Substantial Completion, Contractor shall certify that all remaining Work shall be complete within thirty (30) days or Contractor shall provide a schedule for Final Completion approved in writing by Owner. In the event final completion is not achieved, liquidated damages may be reinstated.
8. Technology cabling shall be in place, tested for connectivity, cable ends terminated and labeled in accordance with the district’s labeling scheme.
9. Fire alarm systems operational, tested, approved, and a graphic map installed.
10. All life safety systems, fire suppression, public address systems, and related items shall be tested and operational.
11. Electronic hardware installation is complete and operational.
12. Paved areas including, but not limited to, parking lots, driveways, curb and gutters, sidewalks, including areas required to be replaced.
13. Certificate of Compliance issued by the city or appropriate authority having jurisdiction for site work.
14. Temporary Certificate of Occupancy or Certificate of Occupancy issued by the city or appropriate authority having jurisdiction with no exceptions or outstanding items.
15. Sanitization of domestic water systems.
16. Verification of floor drains operation, free of obstructions and free-draining.
17. Removal of temporary facilities.
18. Removal of site obstructions, construction debris, and cleanup of site.
19. Submit written request for inspection to Architect and Owner.
20. Warranties will commence on date of Final Substantial Completion.
21. Receipt of approved Operations and Maintenance Manuals including product warranties.
22. Training of Staff.
Appears in 1 contract
Samples: Construction Agreement