Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor shall call for and the Design Professional shall schedule the Final Inspection with the Owner and Contractor. The Design Professional shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional shall issue the Certificate of Final Completion. Final Payment, including any remaining funds withheld may, upon an application for payment, be paid to the Contractor. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call for Final Inspection. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.2.
Appears in 19 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor shall call for and the Design Professional shall schedule the Final Inspection with the Owner and Contractor. The Design Professional shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional shall issue the Certificate of Final Completion. Final Payment, including any remaining funds withheld may, upon an application for payment, be paid to the Contractor. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call for Final Inspection. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.2.fourteen
Appears in 16 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor Owner shall call for and the Design Professional Program Manager shall schedule the Final Inspection with the Owner and ContractorDesign-Builder. The Design Professional Program Manager shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional Program Manager shall issue the Certificate of Final Completion. Completion and Final Payment, including any remaining funds withheld in accordance with Paragraph 6.6.3.2 may, upon an application for payment, be paid to the ContractorDesign-Builder. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call application for Final InspectionPayment. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.2Article 6.2.3.
Appears in 14 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor Owner shall call for and the Design Professional shall schedule the Final Inspection with the Owner and ContractorCM/GC. The Design Professional shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional shall issue the Certificate of Final Completion. Completion and Final Payment, including any remaining funds withheld in accordance with Paragraph 6.6.3.2 may, upon an application for payment, be paid to the ContractorCM/GC. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call application for Final InspectionPayment. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.2Article 6.2.3.
Appears in 13 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor Owner shall call for and the Design Professional Executive Administrator shall schedule the Final Inspection with the Owner and ContractorDesign-Builder. The Design Professional Executive Administrator shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional Executive Administrator shall issue the Certificate of Final Completion. Completion and Final Payment, including any remaining funds withheld in accordance with Paragraph 6.6.3.2 may, upon an application for payment, be paid to the ContractorDesign-Builder. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call application for Final InspectionPayment. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.26.2.3.
Appears in 2 contracts
Samples: Design Build Contract, Construction Contract
Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor shall call for and the Design Professional shall schedule the Final Inspection with the Owner and Contractor. The Design Professional shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional shall issue the Certificate of Final Completion. Final Payment, including any remaining funds withheld may, upon an application for payment, be paid to the Contractor. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call for Final Inspection. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.26.2.3.
Appears in 1 contract
Conducting the Inspection for Final Completion. In the event that Permitted Incomplete Work remains after the Interim Inspection for Punchlist Completion, at such time when all such Permitted Incomplete Work has been completed or scheduled for completion, the Contractor CM/GC shall call for and the Design Professional shall schedule the Final Inspection with the Owner and ContractorCM/GC. The Design Professional shall conduct the Inspection for Final Completion and shall confirm that all Permitted Incomplete and other Work has been completed. Upon successful completion of the inspection, the Design Professional shall issue the Certificate of Final Completion. Final Payment, including any remaining funds withheld may, upon an application for payment, be paid to the ContractorCM/GC. Any Final Documents or updates to Final Documents not yet submitted must be submitted with the call for Final Inspection. In the event any item of Permitted Incomplete Work is determined to be incomplete and the date for its completion has passed, the Owner may give the fourteen (14) day notice of failure to complete the Work set forth in Section 6.2.26.6.5.
Appears in 1 contract
Samples: Construction Management Agreement