Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 5 contracts
Samples: Standard Form of Agreement Between Owner and Contractor, Construction Contract, Standard Form of Agreement Between Owner and Contractor
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner Client and Architect, directing the A/E that directs a change in the Work prior to agreement on and states a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both. It shall be used in the absence of total agreement on the terms of a Change Order. The Owner may by Contractor shall promptly proceed with the change in the Work described in the Construction Change Directive. As soon as possible, without invalidating and within seven days of receipt, the ContractContractor shall advise KCDA and the Client in writing of the Contractor's agreement or disagreement with the cost or the method, order changes if any, provided in the Work within Construction Change Directive for determining the general scope of the Contract consisting of additions, deletions, or other revisions, proposed adjustment in the Contract Sum and or Contract Time being adjusted accordinglyTime.
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 2 contracts
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, /Engineer directing a change in the Work prior to agreement on and stating a proposed basis for adjustment, if any, in the Contract Contact Sum or Contract Time, Time or both. The Owner may may, by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time Times being adjusted accordingly.
Appears in 2 contracts
Samples: Services Agreement, Services Agreement
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect Design Professional and signed by the Owner and ArchitectDesign Professional, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.Work
Appears in 2 contracts
Samples: Construction Manager / General Contractor Agreement, Construction Manager / General Contractor Agreement
Construction Change Directives. 7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 2 contracts
Samples: Contract for Construction, Construction Contract (Digex Inc/De)
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architector Owner, directing a change in the Work prior to agreement on and adjustment, if any, in the Contract Sum Price or Contract Time, time for Substantial Completion or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of this Contract; the Contract consisting of additions, deletions, or other revisions, the Contract Sum Price and Contract Time time for Substantial Completion being adjusted accordingly. A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change Order.
Appears in 1 contract
Samples: Subcontract Agreement
Construction Change Directives. 17.13.1 A Construction Change Directive is a written order prepared and issued by the District, the Construction Manager, and/or the Architect and signed by the Owner District and the Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or bothWork. The Owner may District may, as provided by law, by Construction Change Directive, without invalidating the Contract, order changes Directive and
17.13.2 The District may issue a Construction Change Directive in the Work within absence of agreement on the general scope terms of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordinglya Change Order.
Appears in 1 contract
Samples: General Construction Agreement
Construction Change Directives. 3.1 A Construction Change Directive is a written order prepared by the Architect Owner or at the Owner’s election, the Architect, and signed by the Owner and at the Owner’s election, the Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Architect
Construction Change Directives. 3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and ArchitectOwner, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Sum, GMP, and/or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum Sum, GMP, and Contract Time being adjusted accordingly.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Construction Manager as Constructor
Construction Change Directives. 7.3.1 A Construction Change Directive is a written order [prepared by the Architect Architect] directed to the Contractor and signed by the Owner [and Architectarchitect], directing a change in the Work prior to agreement on and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 1 contract
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect Owner or at the Owner’s election, the Architect, and signed by the Owner and at the Owner’s election, the Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Contractor
Construction Change Directives. 7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by by
7.3.2 A Construction Change Directive, without invalidating the Contract, order changes Directive shall be used in the Work within absence of total agreement on the general scope terms of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordinglya Change Order.
Appears in 1 contract
Samples: General Conditions of the Contract for Construction
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on and stating a proposed basis for adjustment, if any, in the Contract Sum Sum, or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted adjusting accordingly.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Construction Manager as Constructor
Construction Change Directives. A Construction Change Directive is a written order prepared by the Architect Design Agent and signed by the Owner and ArchitectOwner, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 1 contract
Samples: Project Manual
Construction Change Directives. 6.1.1 A Construction Change Directive is a written order prepared by the Architect Architect, after full consultation with and signed and delivered by the Owner and ArchitectAuthority, directing a change in the Work prior to Work. A Construction Change Directive shall be used in the absence of total agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope terms of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordinglya Change.
Appears in 1 contract
Samples: Design Services Agreement
Construction Change Directives. 7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 1 contract
Construction Change Directives. 45 7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and Architect, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
50 7.3.2 A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change Order.
Appears in 1 contract
Samples: General Conditions of the Contract for Construction
Construction Change Directives. § 8.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and ArchitectOwner, directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum Guaranteed Maximum Price or Contract Time, or both. The .
§ 8.3.2 Except as otherwise agreed by the Owner may by Construction Change Directiveand the Design/Builder, without invalidating the adjustment to the Guaranteed Maximum Price shall be determined on the basis of reasonable expenditures and savings of those performing the Work attributable to the change, including the expenditures for design services and revisions to the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions, the Contract Sum and Contract Time being adjusted accordingly.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design/Builder (Magenta Therapeutics, Inc.)