Construction Commencement. Transmission Owner shall commence construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities, Distribution Upgrades, and Generator Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied: 5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; and 5.6.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.
Appears in 30 contracts
Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities, Distribution Upgrades, and Generator Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:Upgrades
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; and
5.6.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.
Appears in 27 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Construction Commencement. The Transmission Owner shall commence construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s Attachment Facilities and System Protection Facilities, Distribution Upgrades, Upgrade Facilities and Generator System Deliverability Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; and
5.6.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.;
Appears in 9 contracts
Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities, Distribution Upgrades, and Generator Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; and
5.6.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 11.5 by the dates specified in Appendix B, Milestones.
Appears in 9 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities, Distribution Upgrades, and Generator Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:Upgrades
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; and
5.6.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 11.5 by the dates specified in Appendix B, Milestones.
Appears in 2 contracts
Samples: Generator Interconnection Agreement, Provisional Generator Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of the Transmission Owner’s Interconnection Facilities, Network Upgrades, Transmission Owner’s System Protection Facilities, Distribution Upgrades, and Generator Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:Transmission
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; and
5.6.2 Where applicable, Interconnection Customer has provided security to Transmission Owner in accordance with Article 11.6 by the dates specified in Appendix B, Milestones.
Appears in 1 contract
Samples: Generator Interconnection Agreement