Construction Commencement. Transmission Owner shall commence construction of Transmission Owner’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied: 5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval; 5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Interconnection Facilities and Network Upgrades; 5.6.3 Transmission Owner has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and 5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 by the dates specified in Appendix B, Milestones.
Appears in 5 contracts
Samples: Generator Interconnection Agreement, Settlement Agreement, Generator Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of Transmission Owner’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Provider Owner in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.
Appears in 5 contracts
Samples: Interconnection Facilities Study Agreement, Interconnection Agreement, Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of Transmission Owner’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.
Appears in 5 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Interconnection Agreement
Construction Commencement. Transmission Owner Provider shall commence construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.
Appears in 5 contracts
Samples: Small Generator Interconnection Agreement (Sgia), Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement (Qf Lgia)
Construction Commencement. Transmission Owner Distribution Provider shall commence construction of Transmission Owner’s Distribution Provider's Interconnection Facilities Facilities, Distribution Upgrades, and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:Network
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Distribution Provider's Interconnection Facilities Facilities, Distribution Upgrades, and Network Upgrades;
5.6.3 Transmission Owner Distribution Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Distribution Provider in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.
Appears in 2 contracts
Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)
Construction Commencement. Transmission Owner Provider shall commence construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-of- way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.
Appears in 2 contracts
Samples: Surplus Large Generator Interconnection Agreement, Surplus Large Generator Interconnection Agreement
Construction Commencement. Transmission Owner shall commence construction of Transmission Owner’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 by the dates specified in Appendix B, Milestones11.7.
Appears in 1 contract
Construction Commencement. Transmission Owner Provider shall commence construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rightsRights-of-way Way have been obtained, to the extent required for the construction of a discrete aspect of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 11.4 by the dates specified in Appendix B, Milestones.
Appears in 1 contract
Construction Commencement. Transmission Owner Provider shall commence construction of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 5.5.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 5.5.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission OwnerProvider’s Interconnection Facilities and Network Upgrades;
5.6.3 5.5.3 Transmission Owner Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; and
5.6.4 5.5.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.
Appears in 1 contract
Samples: Generator Interconnection Agreement
Construction Commencement. The Interconnecting Transmission Owner shall commence construction of the Interconnecting Transmission Owner’s Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Interconnection Facilities and Network Upgrades;the Interconnecting
5.6.3 The Interconnecting Transmission Owner has received written authorization to proceed with construction from the Interconnection Customer by the date specified in Appendix B, B (Milestones); and
5.6.4 The Interconnection Customer has provided security to Interconnecting Transmission Provider Owner in accordance with Article 11.7 11.5 by the dates specified in Appendix B, B (Milestones).
Appears in 1 contract
Construction Commencement. Transmission Owner Provider shall commence construction of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:
5.6.1 Approval of the appropriate Governmental Authority has been obtained for any facilities requiring regulatory approval;approval;
5.6.2 Necessary real property rights and rights-of-way have been obtained, to the extent required for the construction of a discrete aspect of Transmission Owner’s Provider's Interconnection Facilities and Network Upgrades;
5.6.3 Transmission Owner Provider has received written authorization to proceed with construction from Interconnection Customer by the date specified in Appendix B, Milestones; andand
5.6.4 Interconnection Customer has provided security to Transmission Provider in accordance with Article 11.7 11.5 by the dates specified in Appendix B, Milestones.Milestones.
Appears in 1 contract
Samples: Standard Large Generator Interconnection Agreement (Lgia)