CONTRACTOR TO PROVIDE EVERYTHING NECESSARY. The contractor shall provide everything necessary for the proper execution of the work according to the intent and meaning of the drawings, schedule of quantities and specifications taken together whether the same may or may not be particularly shown or described therein provided that the same can reasonably be inferred there from and if the contractor finds any discrepancies therein in shall immediately and in writing, refer the same to the employer/ Architects/ PMC whose decision shall be final and binding. The contractor shall provide himself for ground and fresh water for carrying out of the works at his own cost. The employer shall on no account be responsible for the expenses incurred by the contractor for hired ground or fresh water obtained from elsewhere. The rates quoted against individual items will be inclusive of everything necessary to complete the said items of work within the contemplation of the contract, and beyond the unit price no extra payment will be allowed for incidental or contingent work, labour and/or materials inclusive of all taxes and duties whatsoever except for specific items, if any stipulated in the tender documents. The contractor shall supply, fix and maintain at his own cost, for the execution of any work, all tools, tackles, machineries and equipments and all the necessary centering, scaffolding, staging. Planking, timbering, strutting, shoring, pumping, fencing, boarding, watching and lighting by night as well as by day required not only for the proper execution and protection for the said work but also for the protection of the public and safety of any adjacent roads, streets, walls, house, buildings, all other erections, matters and things and the contractor shall take down and remove any or all such centering, scaffolding, planking, timbering, strutting, shoring etc. as occasion shall be required or when ordered so to do, and shall fully reinstate and make good all matters and things disturbed during the execution of works to the satisfaction of the employer/ Architects. The contractor shall at all times give access to workers employed by the employer or any men employed on the buildings and to provide such parties with proper sufficient and if required, special scaffolding, hoists and ladders and provide them with water and lighting and leave or make any holes, grooves etc. in any work, where directed by the employer as may be required to enable such workmen to lay or fix pipes, electrical wiring, special fittings etc. The quoted rates of the tenderers shall accordingly include all these above mentioned contingent works.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
CONTRACTOR TO PROVIDE EVERYTHING NECESSARY. The contractor shall provide everything necessary for the proper execution of the work according to the intent and meaning of or the drawings, schedule of quantities and specifications taken together whether the same some may or may not be particularly shown or described therein provided that the same can reasonably be inferred there from and if the contractor finds any discrepancies therein in he shall immediately and in writing, refer the same some to the employer/ Architects/ PMC Bank/architects whose decision shall be final and binding. The contractor shall provide himself make his own arrangement for ground and fresh water for carrying out of the works at his own cost. The employer Bank shall on no account be responsible for the expenses incurred by the contractor for hired ground or fresh flesh water obtained from elsewhere. The rates quoted against individual items will be inclusive of everything necessary to complete the said items of work within the contemplation of the contract, and beyond the unit price no extra payment will be allowed for incidental or contingent work, labour . Labour and/or materials inclusive of all taxes and duties whatsoever except for specific items, if any stipulated in the tender documents. The contractor shall supply, fix and maintain at his own cost, for the execution of any work, work all tools, tackles, machineries machinery’s and equipments equipment’s and all the necessary centering, scaffolding, staging. Planking, planking, timbering, strutting, shoring, pumping, fencing, boarding, watching and lighting by night as well as by day required not only for the proper execution and protection for of the said work but also for the protection of the public and safety of any adjacent roads, streets, wallswards, househouses, buildings, all other erections, matters and things and the contractor shall take down and remove any or all such centering, scaffolding, planking, timbering, strutting, shoring etc. ., as occasion shall be required or when ordered so to do, and shall fully reinstate and make good all matters and things tings disturbed during the execution of works to the satisfaction of the employer/ ArchitectsBank/ architects. The contractor shall also provide such temporary road on the site as may be necessary for the proper performance of the contract and for his own convenience but not otherwise. Upon completion, such roads shall be broken up and leveled where so required by the drawings unless the Bank shall other roads shall be broken up and leveled where so required by the drawings unless the employer shall otherwise direct. The contractor shall at all times give access to workers employed by the employer Bank or any men employed on the buildings and to provide such parties with proper sufficient and if required, special scaffolding, hoists and ladders and provide them with water and lighting and leave or make any any, holes, grooves etc. in any work, work where directed by the employer Bank as may be required to enable such workmen to lay or fix pipes, electrical wiring, special fittings etc. The the quoted rates of the tenderers tenders shall accordingly include all these above above-mentioned contingent works.
Appears in 1 contract
Samples: Tender Agreement
CONTRACTOR TO PROVIDE EVERYTHING NECESSARY. a) The contractor shall provide everything necessary at his own cost all materials (except such materials, if any as may in accordance with the contract be supplied by the Employer) plants, tools, appliances, implements, ladders, scaffolding, temporary works, etc. requisite or proper for the proper execution of the work according whether original, altered or substituted and whether included in the specifications or other documents forming part of the contract or which may be necessary for the purpose of satisfying or complying to the intent requirements of Engineer, as to any manner as to which under these conditions he is entitled to be satisfied together with carriage therefore to and meaning from the work. The Contractor shall also supply without charge the requisite number of persons with means and materials necessary for the purpose of setting out works and counting, weighing and assisting in the measurement or examination at any time and from time to time of the drawingswork or materials, schedule of quantities and specifications taken together whether Failing his so doing, the same may or may not be particularly shown or described therein provided that by the same can reasonably be inferred there from and if Engineer at the expense of the contractor finds and the expenses may be deducted from any discrepancies therein in shall immediately and in writing, refer the same money due to the employer/ Architects/ PMC whose decision shall be final and binding. contractor under the contract and/or from his Security Deposit.
b) The contractor Contractor shall provide himself for ground with requisite quantity and fresh quality of water for carrying out of the works at his own cost. If, however, piped water is supplied by the Employer, the contractor shall pay for the water at one per cent of the total cost of the work done except on Electrical work. Air-conditioning work and Furniture work. The employer contractor shall make his own arrangement for water connection and laying of further pipelines from the source of supply of Employer. It should be clearly understood that the Employer does not guarantee to maintain un-interrupted supply of water and it will be incumbent on the part of the contractor to make alternative arrangement for water at his own cost in the event of any temporary break-down in water mains so that progress of work is not held up for want of water. No claim as damages or refund of water charges will be entertained on account of such break-down. However, if the contractor is permitted to make his own arrangement to draw water from a well, hand pump or natural river or pond of the Employer, no charges will be made for the water drawn from the same, but the contractor will make good any damage done to the installations and ensure that the quality of water used in the work is confirming to BIS codes and provide for any treatment at his own cost.
c) The contractor shall be allowed to construct temporary xxxxx in Employer's land for taking water for construction purpose only after he has permission of the Employer in writing. No charges shall be recovered from the contractor on this account but the contractor shall be required to provide necessary safety arrangement to avoid any accident or damage to adjacent buildings, roads and service lines. He shall be responsible for any accident or damage caused due to construction and subsequent maintenance of the xxxxx and shall restore the ground to its original condition after the xxxxx are dismantled on completion of the work.
d) The Employer on no account shall be responsible for the expenses incurred by the contractor for hired ground or fresh water obtained from elsewhere.
e) Subject to availability the Employer may supply power at only one point from where the Contractor shall make his own arrangement for distribution including provision of electric meters, switches, fuses etc. The rates quoted against individual items will be inclusive of everything necessary to complete the said items of work within the contemplation of the contract, and beyond the unit price no extra payment will be allowed for incidental or contingent work, labour and/or materials inclusive of all taxes and duties whatsoever except for specific items, if any stipulated in the tender documents. The contractor shall supply, fix and maintain at his own cost, for . These shall be in the execution of any work, all tools, tackles, machineries and equipments and all the necessary centering, scaffolding, staging. Planking, timbering, strutting, shoring, pumping, fencing, boarding, watching and lighting by night as well as by day required not only for the proper execution and protection for the said work but also for the protection custody of the public and safety of Employer. If there is any adjacent roads, streets, walls, house, buildings, all hindrance caused to other erections, matters and things and works the contractor shall take down and reroute or remove such temporary lines without any or all such centering, scaffolding, planking, timbering, strutting, shoring etcextra cost. as occasion Such temporary lines shall be required or when ordered so to do, and removed after the completion of work. The cost of power consumed by the contractor shall fully reinstate and make good all matters and things disturbed during the execution of works be payable to the satisfaction of the employer/ Architects. The contractor shall employer at all times give access to workers employed rates fixed by the employer Employer, which would be deducted from the running account bills. However the Employer does not guarantee the supply of power and no compensation for any failure or any men employed on the buildings and to provide such parties with proper sufficient and if required, special scaffolding, hoists and ladders and provide them with water and lighting and leave or make any holes, grooves etc. in any work, where directed by the employer as may short supply of power shall be required to enable such workmen to lay or fix pipes, electrical wiring, special fittings etc. The quoted rates of the tenderers shall accordingly include all these above mentioned contingent worksentertained.
Appears in 1 contract
Samples: General Conditions of Contract
CONTRACTOR TO PROVIDE EVERYTHING NECESSARY. 21.1 The contractor CONTRACTOR shall provide everything necessary for the proper execution of the work Works according to the intent and meaning of the drawings, schedule of quantities and specifications taken together whether the same may or may not be particularly shown or described therein provided that the same can reasonably be inferred there from and if the contractor CONTRACTOR finds any discrepancies discrepancy therein in shall immediately and in writing, writing refer the same to the employer/ Architects/ PMC ENGINEER whose decision shall be final and binding. binding on the parties.
21.2 The contractor shall provide himself for ground and fresh water for carrying out of the works at his own cost. The employer shall on no account be responsible for the expenses incurred by the contractor for hired ground or fresh water obtained from elsewhere. The rates quoted against individual items will be inclusive of everything necessary to complete the said items of work within the contemplation of the contract, and beyond the unit price no extra payment will be allowed for incidental or contingent work, labour and/or materials inclusive of all taxes and duties whatsoever except for specific items, if any stipulated in the tender documents. The contractor CONTRACTOR shall supply, fix and maintain at his own cost, for during the execution of any work, all tools, tackles, machineries and equipments and works all the necessary centeringcantering, scaffolding, staging. Planking, planking, timbering, strutting, shoring, pumping, fencing, boardinghoarding, watching and lighting by night as well as by day day, etc required not only for the proper execution and protection for of the said work Works, but also for the protection of the public and the safety of any adjacent roads, streets, cellars, vaults, walls, househouses, buildings, buildings and all other erections, matters and things or things, and the contractor CONTRACTOR shall take down out and remove any or all such centeringcantering, scaffolding, staging, planking, timbering, strutting, shoring etc. as occasion shall be required require or when ordered to do so to do, and shall fully reinstate and make good all matters and things disturbed during the execution of the works to the satisfaction of the employer/ ArchitectsENGINEER. The CONTRACTOR shall be paid no additional amount for the above and for any access roads to be made to reach the construction site.
21.3 All materials shall be new and of the best respective kinds described in the schedule of quantities and/or Technical Specifications and in accordance with the Engineer’s Instructions and the CONTRACTOR shall upon the request of the ENGINEER, furnish him with all invoices, accounts, receipts, certificates and other vouchers, to prove that the materials comply therewith. The CONTRACTOR shall at his own cost arrange for and/or carry out any test of materials which the ENGINEER may require. The contractor shall establish and operate a full- fledged cement and concrete testing laboratory at site and depute a full time qualified QA/QC engineer for the duration of the contract at no extra cost to the Owner/Project Manager. Such full-fledged cement and concrete testing laboratory at the site shall be as per provision of IS: 456 and CONTRACTOR shall also depute an independent qualified QA/QC engineer full-time at the site for the duration of the contract.
21.4 It shall be the responsibility of the CONTRACTOR to unload and store in a safe and acceptable manner all times give access to workers employed construction materials as directed by the employer or any men employed on the buildings and Owner/Project Manager.
21.5 The CONTRACTOR is required to provide and maintain all tools, and equipment and instruments necessary to perform his work. He shall provide all fuels, lubricants and compressed air for the operation and maintenance of his construction tools.
21.6 The CONTRACTOR is to arrange for all his requirements of such parties materials including but not limited to oxygen, Acetylene, pipes, ropes, welding rods etc required for performing the Works.
21.7 Samples of all materials to be used, whether cement, steel, bricks, rubble stone, aggregate, sand, timber, tiles, granite, finishing & building interior etc. shall be submitted by the CONTRACTOR and must be got approved by the Owner/Project Manager before they are used. Approved samples shall be kept with proper sufficient the Owner/Project Manager and if requiredall supplies shall strictly conform to the approved samples. Materials not strictly conforming to the samples are liable to the rejected.
21.8 The CONTRACTOR shall not sell, special scaffoldingassign, hoists mortgage, hypothecate or remove equipment or materials which have been installed or which may be necessary for the completion of the Contract without the written consent of the Owner/Project Manager.
21.9 CONTRACTOR shall provide and ladders maintain at the site necessary number and provide them with water type of machinery and lighting and leave or make any holesequipment including survey instruments, grooves TOTAL Station, Auto level etc. in any work, where directed good working condition for proper setting out and timely completion of the various works covered under Relevant Package. All arrangements for transporting the equipment to and from the site shall be done by the employer CONTRACTOR at his own expense. Contractor has to provide all the survey equipments including all technicians, helpers etc., for checking other works also if so desired by Owner with no additional cost of the Owner. No claim shall be entertained for mobilising additional equipment and/or personnel to complete the work within the stipulated time.
21.10 CONTRACTOR shall provide all fuels and lubricants required for the operation and maintenance of construction machinery and equipment as may well as his transport vehicles.
21.11 CONTRACTOR shall at his cost arrange for all his requirements of such materials as, but not limited to, oxygen, acetylene, welding electrodes, ropes, form ties, turn-buckles, clamps, wiping rags and sand papers etc. which are required to satisfactorily perform his work.
21.12 It shall be ensured by the CONTRACTOR that work shall proceed uninterrupted even in the event of power failures with the help of DG Sets and Diesel compressors. As such, adequate number of diesel operated machinery (such as boring rigs, concrete mixers, vibrators, welding sets, etc.) shall be provided by the CONTRACTOR as an alternative arrangement in case electrically operated machinery are proposed to be brought to site.
21.13 The CONTRACTOR will be required to enable such workmen provide at his own cost all facilities for his office, warehouse, tool room, change room or any other building/structure required to lay or fix pipesthe Works.
21.14 CONTRACTOR shall establish his own office / shed at specified place inside/near the project site for his worker/staff. The CONTRACTOR’s office/shed shall be porta-cabin type. Only the shed for storing Cement shall be in brick masonry. In addition the office/shed shall have proper ventilation lighting and sanitary facilities. CONTRACTOR shall plan their site facilities and obtain clearance from the OWNER before construction of the Office/shed.
21.15 All royalties shall be paid by the CONTRACTOR as also all tolls, electrical wiringlocal and other taxes, special fittings etc. at no extra cost to OWNER. The rates quoted rates for excavation shall include Collector’s permissions for
21.16 All materials supplied by the CONTRACTOR shall be of the tenderers best quality and shall accordingly include conform to the Technical Specification. Approval in writing shall be obtained from OWNER before any alternative or equivalent material is proposed to be used by the CONTRACTOR.
21.17 The CONTRACTOR shall get tested all materials supplied by him in a OWNER approved laboratory, as directed by ENGINEER or as specified in the corresponding code of practice, at no extra cost to the OWNER. This is in addition to furnishing the Manufacturer’s Test Certificate where available.
21.18 CONTRACTOR shall obtain all necessary permits and licenses before commencement of work at no extra cost to OWNER.
21.19 The CONTRACTOR shall have PF coverage, for all workmen in his permanent employee as well as those temporarily hired by him for the said project. He shall also have ESIC cover for all workmen, permanent as well as temporary if required by law. The cost for both the above viz. PF as well as ESIC shall be deemed to have been covered in the rate quoted by contractor. The OWNER shall not pay any extra charges over and above the rates quoted for these above mentioned contingent worksstatutory payments.
Appears in 1 contract