Contractor’s Construction Documents Stage Submission. 5.5.1 At the completion of the activities described under Section 5.4 and based on the provisional Construction Documents, the Contractor will submit its Construction Documents Stage Submission. 5.5.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Construction Documents Stage Submission, the Contractor will include in its Construction Documents Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Construction Documents Estimate”). 5.5.2.1 If the Contractor’s Construction Documents Estimate exceeds the Construction Budget or varies from the A/E’s Construction Documents Estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Construction Documents Stage Submission. 5.5.3 If a GMP Amendment has been entered into at the time of the Contractor’s Construction Documents Stage Submission, the Contractor shall include with the Contractor’s Construction Documents Stage Submission a detailed description of any change in the scope of the Work described in the provisional Construction Documents as compared to the scope of the Work described in the GMP Documents and an estimate of the cost and time impact of each change.
Appears in 2 contracts
Samples: Architect/Engineer Agreement, Architect/Engineer Agreement
Contractor’s Construction Documents Stage Submission. 5.5.1 At the completion of the activities described under Section 5.4 and based on the provisional Construction Documents, the Contractor will submit its Construction Documents Stage Submission.
5.5.2 If all of the Work is not subject to an executed GMP Amendment at the time of the Contractor’s Construction Documents Stage Submission, the Contractor will include in its Construction Documents Stage Submission the Contractor’s estimate of Construction Costs (“Contractor’s Construction Documents Estimate”).
5.5.2.1 If the Contractor’s Construction Documents Estimate exceeds the Construction Budget or varies from the A/E’s Construction Documents EstimateEstimate by more than 5 percent of that estimate, the Contracting Authority may require the A/E to immediately work with the Contractor to develop viable proposals to reconcile the estimates with each other and the Construction Budget. The Contractor will present those proposals as an addendum to its Construction Documents Stage Submission.
5.5.3 If a GMP Amendment has been entered into at the time of the Contractor’s Construction Documents Stage Submission, the Contractor shall include with the Contractor’s Construction Documents Stage Submission a detailed description of any change in the scope of the Work described in the provisional Construction Documents as compared to the scope of the Work described in the GMP Documents and an estimate of the cost and time impact of each change.