Contractor’s Termination Right Sample Clauses

Contractor’s Termination Right. Subject to Applicable Law, if, at the end of the suspension period specified pursuant to Section 20.4, Owner has not requested a resumption of the Work or has not notified Contractor of any extension of the suspension period (but in no event beyond one hundred eighty (180) days in the aggregate for all such suspensions, other than suspensions for any reason due to Contractor’s negligence, willful misconduct or noncompliance with the material terms of this Agreement) at Contractor’s option this Agreement shall be deemed terminated as of the commencement date of the suspension period, and Owner shall promptly pay Contractor for the Work performed pursuant to Section 20.1. In the event the Full Notice to Proceed has not been issued by December 31, 2007, Contractor may, upon ten (10) days prior Notice to Owner, terminate this Agreement and Owner shall pay Contractor for the Work performed pursuant to Section 20.1. Notwithstanding anything to the contrary herein, Contractor shall not be entitled to terminate this Agreement regardless of the number of days a Suspension for Cause (as defined in Section 20.6) may extend.
Contractor’s Termination Right. Subject to Applicable Law, if, at the end of the suspension period specified pursuant to this Section 20.7, Owner has not requested a resumption of the Work or has not notified Contractor of any extension of the suspension period (but in no event beyond three hundred sixty-five (365) days in the aggregate for all such suspensions, other than Suspensions for Cause) at Contractor’s option, Contractor may perform such Work as is necessary to close out the Project in a prudent manner and this Agreement shall be deemed terminated as of the date such Work is completed, but in no event more than ten (10) days after such suspension period has ended. Owner shall pay Contractor for the Work performed pursuant to Section 20.1. Notwithstanding anything to the contrary herein, Contractor shall not be entitled to terminate this Agreement regardless of the number of days a Suspension for Cause may extend.
Contractor’s Termination Right. (a) If at the end of the specified suspension period Owner has not requested a resumption of the Work or has not notified Contractor of any extension of the suspension period (but in no event beyond one hundred eighty (180) days in the aggregate for all suspensions under this Contract, other than suspensions for any reason due to Contractor’s negligence, willful misconduct or noncompliance with the terms of this Contract) at Contractor’s option the Work shall be deemed terminated as of the commencement date of the suspension period, and Owner shall pay Contractor in accordance with Section 21.1.1. (b) Contractor shall have the right to suspend Work in the event of an Owner Event of Default (including for failure to make payment of money indisputably owed to Contractor to the extent, and within the time periods, provided in Section 20.4(f)) as provided in Section 20.5(b).