Coordination with City. In performing services under this Agreement, Consultant shall coordinate all contact with City through its Agreement Administrator. All changes and/or extra work shall be performed and paid for in accordance with the following: 5.2.1. Only the City Engineer may authorize extra and/or changed work. Consultant expressly recognizes that other City personnel are without authorization to either order extra and/or changed work or waive contract requirements. Failure of Consultant to secure the Council's or City Engineer's authorization for such extra and/or changed work shall constitute a waiver of any and all right to adjustment in contract price due to such unauthorized work and Consultant thereafter shall be entitled to no compensation whatsoever for performance of such work. 5.2.2. If the Consultant is of the opinion that any work s/he has been directed to perform is beyond the scope of this Agreement and constitutes extra work, s/he shall promptly notify the City of the fact. The City shall make a determination as to whether or not such work is, in fact, beyond the scope of this Agreement and constitutes extra work. In the event that the City determines that such work does constitute extra work, it shall provide extra compensation to the Consultant on a fair and equitable basis. A Supplemental Agreement providing for such compensation for extra work shall be negotiated between the City and the Consultant. Such Supplemental Agreement shall be executed by the Consultant and be approved by the City Manager or City Engineer. 5.2.3. In the event City determines that such work does not constitute extra work, Consultant shall not be paid extra compensation above that provided herein and if such determination is made by City staff, said determination may be appealed to the City Council as long as a written appeal is submitted to the City Manager within five (5) days after the staff's determination is received by the Consultant. Said written appeal shall include a description of each and every ground upon which Consultant challenges the staff's determination. The City Manager’s or City Engineer’s decision shall be final.
Appears in 1 contract
Samples: Professional Services
Coordination with City. In performing services under this Agreement, Consultant shall coordinate all contact with City through its Agreement Administrator. All changes and/or extra work shall be performed and paid for in accordance with the following:
5.2.1. Only the Agreement Administrator or City Engineer Council may authorize extra and/or changed work. Consultant expressly recognizes that other City personnel are without authorization to either order extra and/or changed work or waive contract requirements. Failure of Consultant to secure the Council's or City Engineer's authorization for such extra and/or changed work shall constitute a waiver of any and all right to adjustment in contract price due to such unauthorized work and Consultant thereafter shall be entitled to no compensation whatsoever for performance of such work.
5.2.2. If the Consultant is of the opinion that any work s/he has been directed to perform is beyond the scope of this Agreement and constitutes extra work, s/he shall promptly notify the City of the fact. The City shall make a determination as to whether or not such work is, in fact, beyond the scope of this Agreement and constitutes extra work. In the event that the City determines that such work does constitute extra work, it shall provide extra compensation to the Consultant on a fair and equitable basis. A Supplemental Agreement providing for such compensation for extra work shall be negotiated between the City and the Consultant. Such Supplemental Agreement shall be executed by the Consultant and be approved by the City Manager or City Engineer.
5.2.3. In the event City determines that such work does not constitute extra work, Consultant shall not be paid extra compensation above that provided herein and if such determination is made by City staff, said determination may be appealed to the City Council as long as a written appeal is submitted to the City Manager within five (5) days after the staff's determination is received by the Consultant. Said written appeal shall include a description of each and every ground upon which Consultant challenges the staff's determination. The City Manager’s or City Engineer’s the Agreement Administrator decision shall be final.
Appears in 1 contract
Samples: Professional Services
Coordination with City. In performing services under this Agreement, Consultant shall coordinate all contact with City through its Agreement Administrator. All changes and/or extra work shall be performed and paid for in accordance with the following:
5.2.1. Only the City Engineer or City Council may authorize extra and/or changed work. Consultant expressly recognizes that other City personnel are without authorization to either order extra and/or changed work or waive contract requirements. Failure of Consultant to secure the Council's or City Engineer's authorization for such extra and/or changed work shall constitute a waiver of any and all right to adjustment in contract price due to such unauthorized work and Consultant thereafter shall be entitled to no compensation whatsoever for performance of such work.
5.2.2. If the Consultant is of the opinion that any work s/he has been directed to perform is beyond the scope of this Agreement and constitutes extra work, s/he shall promptly notify the City of the fact. The City shall make a determination as to whether or not such work is, in fact, beyond the scope of this Agreement and constitutes extra work. In the event that the City determines that such work does constitute extra work, it shall provide extra compensation to the Consultant on a fair and equitable basis. A Supplemental Agreement providing for such compensation for extra work shall be negotiated between the City and the Consultant. Such Supplemental Agreement shall be executed by the Consultant and be approved by the City Manager or City Engineer.
5.2.3. In the event City determines that such work does not constitute extra work, Consultant shall not be paid extra compensation above that provided herein and if such determination is made by City staff, said determination may be appealed to the City Council as long as a written appeal is submitted to the City Manager within five (5) days after the staff's determination is received by the Consultant. Said written appeal shall include a description of each and every ground upon which Consultant challenges the staff's determination. The City Manager’s or City Engineer’s decision shall be final.
Appears in 1 contract
Samples: Professional Services
Coordination with City. In performing services under this Agreement, Consultant shall coordinate all contact with City through its Agreement Administrator. All changes and/or extra work shall be performed and paid for in accordance with the following:
5.2.1. Only the City Engineer [enter department head] or City Council may authorize extra and/or changed work. Consultant expressly recognizes that other City personnel are without authorization to either order extra and/or changed work or waive contract requirements. Failure of Consultant to secure the Council's or City Engineer's [enter department head]’s authorization for such extra and/or changed work shall constitute a waiver of any and all right to adjustment in contract price due to such unauthorized work and Consultant thereafter shall be entitled to no compensation whatsoever for performance of such work.
5.2.2. If the Consultant is of the opinion that any work s/he has been directed to perform is beyond the scope of this Agreement and constitutes extra work, s/he shall promptly notify the City of the fact. The City shall make a determination as to whether or not such work is, in fact, beyond the scope of this Agreement and constitutes extra work. In the event that the City determines that such work does constitute extra work, it shall provide extra compensation to the Consultant on a fair and equitable basis. A Supplemental Agreement providing for such compensation for extra work shall be negotiated between the City and the Consultant. Such Supplemental Agreement shall be executed by the Consultant and be approved by the City Manager or City Engineer[enter department head].
5.2.3. In the event City determines that such work does not constitute extra work, Consultant shall not be paid extra compensation above that provided herein and if such determination is made by City staff, said determination may be appealed to the City Council as long as a written appeal is submitted to the City Manager within five (5) days after the staff's determination is received by the Consultant. Said written appeal shall include a description of each and every ground upon which Consultant challenges the staff's determination. The City Manager’s or City Engineer[enter department head]’s decision shall be final.